[PJ250016] Management system stock and process "Pegasus" #1

Added by Kittisak Isarapongporn 10 months ago. Updated 4 days ago.

Status:
In Progress
Priority:
Normal
Start date:
01 Apr 2025
Due date:
01 Apr 2026 (Due in 56 days)
Spent time:
(Total: 18.00 h)

Files


Subtasks 65 (23 open42 closed)

Project progress work #912: [Documentation] Get requirements of projectClosedRonnagon Kongsuwan01 Apr 202530 Jun 2025

Actions
Project progress work #1116: [Requirement definition]ClosedRonnagon Kongsuwan22 Apr 202508 Jun 2025

Actions
Project progress work #1117: [Internal Design]ClosedRonnagon Kongsuwan05 Aug 202511 Dec 2025

Actions
Project progress work #1118: [Coding]NewRonnagon Kongsuwan09 Oct 202503 Feb 2026

Actions
Project progress work #1710: [Coding] Master Data -WH,PDClosedRonnagon Kongsuwan09 Oct 202514 Oct 2025

Actions
Project progress work #1711: [Coding] Inbound - Outbound Inquiry, Tracking, Tag Label Page -WHClosedRonnagon Kongsuwan15 Oct 202519 Oct 2025

Actions
Project progress work #1712: [Coding] Import Purchase Order -WHClosedRonnagon Kongsuwan20 Oct 202520 Oct 2025

Actions
Project progress work #1713: [Coding] Import Schedule Raw Material Receiving (Plan) -WHClosedRonnagon Kongsuwan21 Oct 202521 Oct 2025

Actions
Project progress work #2817: [Coding] Inbound Material Page -WHClosedRonnagon Kongsuwan22 Oct 202526 Oct 2025

Actions
Project progress work #2818: [Coding] Purchase Order Page -WHClosedRonnagon Kongsuwan27 Oct 202528 Oct 2025

Actions
Project progress work #2819: [Coding] Print Purchase Order Domestic -WHClosedRonnagon Kongsuwan29 Oct 202531 Oct 2025

Actions
Project progress work #2820: [Coding] Print Purchase Order International -WHClosedRonnagon Kongsuwan01 Nov 202504 Nov 2025

Actions
Project progress work #2821: [Coding] IQC Material Page -WHClosedRonnagon Kongsuwan05 Nov 202506 Nov 2025

Actions
Project progress work #2822: [Coding] Import Schedule Raw Material Request (Plan) -WH,PDClosedRonnagon Kongsuwan07 Nov 202507 Nov 2025

Actions
Project progress work #2823: [Coding] Raw Material Request Page -WH,PDClosedRonnagon Kongsuwan08 Nov 202511 Nov 2025

Actions
Project progress work #2824: [Coding] Print Raw Material Request -WH,PDClosedRonnagon Kongsuwan12 Nov 202513 Nov 2025

Actions
Project progress work #2825: [Coding] Import Schedule FG Production (Plan) -PDClosedRonnagon Kongsuwan14 Nov 202514 Nov 2025

Actions
Project progress work #2826: [Coding] Inbound Production Page -PDClosedRonnagon Kongsuwan15 Nov 202521 Nov 2025

Actions
Project progress work #2827: [Coding] Outbound Material Usage Page -PDClosedRonnagon Kongsuwan22 Nov 202526 Nov 2025

Actions
Project progress work #2828: [Coding] IQC FG Page -PDClosedRonnagon Kongsuwan27 Nov 202530 Nov 2025

Actions
Project progress work #2829: [Coding] Outbound FG (Production) To WH Page -WH,PDClosedRonnagon Kongsuwan22 Dec 202526 Dec 2025

Actions
Project progress work #2830: [Coding] Print Finished Goods Pay In Stock Sheet -PDClosedRonnagon Kongsuwan05 Jan 202606 Jan 2026

Actions
Project progress work #2831: [Coding] Outbound Delivery Page -WHClosedRonnagon Kongsuwan07 Jan 202610 Jan 2026

Actions
Project progress work #2832: [Coding] Stock Management -WHClosedRonnagon Kongsuwan11 Jan 202613 Jan 2026

Actions
Project progress work #6400: [Coding] Stock InquiryNewRonnagon Kongsuwan30 Jan 202630 Jan 2026

Actions
Project progress work #6401: [Coding] Stock MaintenanceNewRonnagon Kongsuwan30 Jan 202630 Jan 2026

Actions
Project progress work #6402: [Coding] Stock Movement Transfer ReportNewRonnagon Kongsuwan31 Jan 202631 Jan 2026

Actions
Project progress work #6403: [Coding] Stock Inventory ReportNewRonnagon Kongsuwan31 Jan 202631 Jan 2026

Actions
Project progress work #6404: [Coding] Tag LabelNewRonnagon Kongsuwan02 Feb 202602 Feb 2026

Actions
Project progress work #6405: [Coding] StocktakingNewRonnagon Kongsuwan03 Feb 202603 Feb 2026

Actions
Project progress work #3153: [Coding] NewSoraya Norasing26 Nov 202522 Dec 2025

Actions
Project progress work #3154: [Coding] Setting / Login / Main MenuClosedSoraya Norasing26 Nov 202526 Nov 2025

Actions
Project progress work #3155: [Coding] Inbound Schedule (No rank)ClosedSoraya Norasing27 Nov 202503 Dec 2025

Actions
Project progress work #3156: [Coding] Inbound Schedule (Rank A B)ClosedSoraya Norasing04 Dec 202509 Dec 2025

Actions
Project progress work #3157: [Coding] Inbound ManualClosedSoraya Norasing10 Dec 202511 Dec 2025

Actions
Project progress work #3158: [Coding] Confirm ReceiveClosedSoraya Norasing12 Dec 202513 Dec 2025

Actions
Project progress work #3159: [Coding] QC CheckNewSoraya Norasing15 Dec 202520 Dec 2025

Actions
Project progress work #3160: [Coding] QC Schedule ClosedSoraya Norasing15 Dec 202518 Dec 2025

Actions
Project progress work #3161: [Coding] QC Check ManualClosedSoraya Norasing19 Dec 202522 Dec 2025

Actions
Project progress work #3162: [Coding] Work Outbound ClosedSoraya Norasing26 Nov 202501 Dec 2025

Actions
Project progress work #3163: [Coding] Delivery OutboundClosedSoraya Norasing02 Dec 202504 Dec 2025

Actions
Project progress work #3164: [Coding] Outbound CrusherNewSoraya Norasing08 Dec 202510 Dec 2025

Actions
Project progress work #3165: [Coding] Outbound ManualClosedSoraya Norasing11 Dec 202512 Dec 2025

Actions
Project progress work #3166: [Coding] Stock managementClosedSoraya Norasing13 Dec 202515 Dec 2025

Actions
Project progress work #3167: [Coding] Printer SettingNewSoraya Norasing15 Dec 202515 Dec 2025

Actions
Project progress work #3168: [Coding] Label Template ClosedSoraya Norasing15 Dec 202519 Dec 2025

Actions
Project progress work #6406: [Coding] TestNew08 Jan 202622 Feb 2026

Actions
Project progress work #6407: [Test] Unit Test Inbound #1ClosedRonnagon Kongsuwan08 Jan 202608 Jan 2026

Actions
Project progress work #6408: [Test] Unit Test Inbound #2ClosedRonnagon Kongsuwan14 Jan 202614 Jan 2026

Actions
Project progress work #6409: [Test] Unit Test Outbound #1ClosedRonnagon Kongsuwan09 Jan 202609 Jan 2026

Actions
Project progress work #6410: [Test] Unit Test Outbound #2ClosedRonnagon Kongsuwan15 Jan 202615 Jan 2026

Actions
Project progress work #6411: [Test] Unit Test QC Check #1ClosedRonnagon Kongsuwan20 Jan 202620 Jan 2026

Actions
Project progress work #6412: [Test] Unit Test Inbound & Outbound #3ClosedRonnagon Kongsuwan27 Jan 202627 Jan 2026

Actions
Project progress work #6413: [Test] Unit Test QC Check #2ClosedRonnagon Kongsuwan29 Jan 202629 Jan 2026

Actions
Project progress work #6414: [Test] Unit Test Slitting & Stock managementNewRonnagon Kongsuwan02 Feb 202602 Feb 2026

Actions
Project progress work #6415: [Test] Label PrintingNewRonnagon Kongsuwan05 Feb 202605 Feb 2026

Actions
Project progress work #6416: [Test] System TestNewRonnagon Kongsuwan09 Feb 202622 Feb 2026

Actions
Project progress work #6417: [Installation&On-site support]NewRonnagon Kongsuwan25 Feb 202601 Apr 2026

Actions
Project progress work #6418: [Installation&On-site support] Hardware installationNewRonnagon Kongsuwan25 Feb 202626 Feb 2026

Actions
Project progress work #6419: [Installation&On-site support] Software installation NewRonnagon Kongsuwan27 Feb 202602 Mar 2026

Actions
Project progress work #6420: [Installation&On-site support] Teaching for UT NewRonnagon Kongsuwan04 Mar 202606 Mar 2026

Actions
Project progress work #6421: [Installation&On-site support] User Testing & Trial NewRonnagon Kongsuwan09 Mar 202631 Mar 2026

Actions
Project progress work #6422: [Installation&On-site support] Supports user feedback NewRonnagon Kongsuwan09 Mar 202631 Mar 2026

Actions
Project progress work #6423: [Installation&On-site support] Teaching for Go live NewRonnagon Kongsuwan01 Apr 202601 Apr 2026

Actions
Project progress work #6424: [Installation&On-site support] Go live NewRonnagon Kongsuwan01 Apr 202601 Apr 2026

Actions
Actions #1

Updated by Kittisak Isarapongporn 10 months ago

  • Project changed from TOMAS TECH CO., LTD. to MITSUI PRECISION THAI CO., LTD.
Actions #2

Updated by Karnthida Wannasiwaporn 10 months ago

  • Subject changed from [PJ250015] Production management system to [PJ250016] Production management system
Actions #3

Updated by Siriporn Nimitmuenwai 6 months ago

  • Subject changed from [PJ250016] Production management system to [PJ250016] Management system stock and process "Pegasus" #1
  • Assignee set to Ronnagon Kongsuwan
Actions #4

Updated by Siriporn Nimitmuenwai 5 months ago

  • File 【Gantt chart】Project schedule for Mitsui of Customer_R2.xlsx added
Actions #6

Updated by Siriwilai Chaiwattanaphon 4 days ago