Project progress work #6417

closed

Parent project #911: [PJ250016] Management system stock and process "Pegasus" #1

[Installation&On-site support]

Added by Siriwilai Chaiwattanaphon about 2 months ago. Updated 3 days ago.

Status:
Closed
Priority:
Normal
Start date:
16 Feb 2026
Due date:
01 Apr 2026
% Done:

100%

Estimated time:
(Total: 440.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 14 (0 open14 closed)

Project progress work #6418: [Installation&On-site support] Hardware installationClosedRonnagon Kongsuwan25 Feb 202626 Feb 2026

Actions
Project progress work #6419: [Installation&On-site support] Software installation ClosedRonnagon Kongsuwan27 Feb 202602 Mar 2026

Actions
Project progress work #6420: [Installation&On-site support] Teaching for UT ClosedRonnagon Kongsuwan04 Mar 202606 Mar 2026

Actions
Project progress work #6421: [Installation&On-site support] User Testing & Trial ClosedRonnagon Kongsuwan09 Mar 202631 Mar 2026

Actions
Project progress work #6422: [Installation&On-site support] Supports user feedback ClosedRonnagon Kongsuwan09 Mar 202631 Mar 2026

Actions
Project progress work #6423: [Installation&On-site support] Teaching for Go live ClosedRonnagon Kongsuwan01 Apr 202601 Apr 2026

Actions
Project progress work #6424: [Installation&On-site support] Go live ClosedRonnagon Kongsuwan01 Apr 202601 Apr 2026

Actions
Project progress work #6663: [Installation&On-site support] Deploy Database and Source Code to Cloud.ClosedRonnagon Kongsuwan16 Feb 202616 Feb 2026

Actions
Project progress work #6753: [Installation&On-site support] Present Project Progress Onsite Check Data Master.ClosedRonnagon Kongsuwan19 Feb 202619 Feb 2026

Actions
Project progress work #6771: [Installation&On-site support] Onsite Install.ClosedRonnagon Kongsuwan25 Feb 202626 Feb 2026

Actions
Project progress work #6902: [Installation&On-site support] Onsite Training.ClosedRonnagon Kongsuwan04 Mar 202605 Mar 2026

Actions
Project progress work #6992: [Installation&On-site support] Setup Printer, Update Code Based on Customer Requests, and Provide Onsite User SupportClosedRonnagon Kongsuwan12 Mar 202613 Mar 2026

Actions
Project progress work #6994: [Installation&On-site support] InstallationClosedSoraya Norasing25 Feb 202626 Feb 2026

Actions
Project progress work #6995: [Installation&On-site support] Traning UserClosedSoraya Norasing04 Mar 202606 Mar 2026

Actions
Actions #1

Updated by Waraporn Promsopa about 1 month ago

  • Status changed from New to Closed
Actions #2

Updated by Waraporn Promsopa 23 days ago

  • Status changed from Closed to In Progress
Actions #3

Updated by Waraporn Promsopa 3 days ago

  • Status changed from In Progress to Closed
Actions #4

Updated by Waraporn Promsopa 3 days ago

  • Status changed from Closed to In Progress
Actions #5

Updated by Waraporn Promsopa 3 days ago

  • Status changed from In Progress to Closed
Actions #6

Updated by Waraporn Promsopa 3 days ago

  • Status changed from Closed to In Progress
Actions #7

Updated by Waraporn Promsopa 3 days ago

  • Status changed from In Progress to Closed
Actions

Also available in: Atom PDF