Project progress work #1116

open

Parent project #911: [PJ250016] Management system stock and process "Pegasus" #1

[Requirement definition]

Added by Siriporn Nimitmuenwai 10 months ago. Updated 8 days ago.

Status:
In Progress
Priority:
Normal
Start date:
17 Mar 2026
Due date:
26 May 2026 (25 days late)
% Done:

100%

Estimated time:
272.00 h (Total: 336.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 2 (0 open2 closed)

Project progress work #7100: [Requirement definition] Rewrite Manual DocumentClosedPhan Mai Son17 Mar 202625 Mar 2026

Actions
Project progress work #8527: [Requirement definition] Onsite meeting at Mitsui to review project progress and discuss remaining issues.ClosedRonnagon Kongsuwan26 May 202626 May 2026

Actions
Actions #1

Updated by Siriporn Nimitmuenwai 10 months ago

  • Due date changed from 10 Sep 2025 to 08 Jun 2025
  • Start date changed from 26 May 2025 to 22 Apr 2025
  • % Done changed from 0 to 100
  • Estimated time set to 272.00 h
Actions #2

Updated by Siriporn Nimitmuenwai 10 months ago

  • Status changed from New to In Progress
Actions #3

Updated by Siriwilai Chaiwattanaphon 8 months ago

  • Status changed from In Progress to Closed
Actions #4

Updated by Waraporn Promsopa 3 months ago

  • Status changed from Closed to In Progress
Actions