For internal project work assignment report without Nozaki

Apply Clear

Estimated time: 18864.00 Spent time: 7808.40

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
891 Project progress work New Normal For internal meeting and other Panthita Roekdee 376.00 856.00 02 Apr 2025 16:30 Actions
714 Project progress work New Normal For internal meeting and other Panthita Roekdee 1096.00 1592.00 20 Mar 2025 16:49 Actions
614 Project progress work New Normal (Power Meter and CT ) Wiring and Installation Panupong Raksakit 348.00 88.00 16 Nov 2024 12:23 Actions
764 Project progress work New Normal FTP DATA LOGGING Panupong Raksakit 300.00 168.00 16 Nov 2024 10:43 Actions
763 Project progress work New Normal ANDON DASHBOARD DESIGN AND PROGRAMMING Panupong Raksakit 600.00 304.00 16 Nov 2024 10:43 Actions
517 Project progress work New Normal Panupong Raksakit Taking Day off January-December 2024 Panupong Raksakit 80.00 40.00 04 May 2024 17:22 Actions
2949 Project progress work New Normal [Installation&On-site support] Utility monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2950 Project progress work New Normal [Installation&On-site support] Utility data monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2951 Project progress work New Normal [Installation&On-site support] Air flow monitoring Panupong Raksakit 8.00 0.00 18 Nov 2025 16:56 Actions
3301 Project progress work In Progress Normal [Installation&On-site support] Go live Pattanasak Chaonchom 16.00 0.00 18 Dec 2025 14:35 Actions
3321 Project progress work New Normal [Coding] Validation check Signal & Information Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3320 Project progress work New Normal [Coding] WDT Configuration Line 5 Pattanasak Chaonchom 0.00 19 Dec 2025 09:22 Actions
3319 Project progress work New Normal [Coding] Validation check Signal & Information Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:24 Actions
3318 Project progress work New Normal [Coding] WDT Configuration Line 4 Pattanasak Chaonchom 0.00 19 Dec 2025 09:21 Actions
3317 Project progress work New Normal [Coding] Validation check Signal & Information Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:23 Actions
3316 Project progress work New Normal [Coding] WDT Configuration Line 3 Pattanasak Chaonchom 8.00 0.00 19 Dec 2025 09:19 Actions
3330 Project progress work New Normal [Installation&On-site support] Software installation Pattanasak Chaonchom 40.00 0.00 19 Dec 2025 10:38 Actions
3191 Project progress work New Normal [Coding] Development and modification Phattarapong Kammee 0.00 11 Dec 2025 14:03 Actions
1407 Project progress work New Normal [Coding] Electric summary Phattarapong Kammee 0.00 05 Nov 2025 11:39 Actions
1406 Project progress work New Normal [Coding] Sync data Phattarapong Kammee 0.00 05 Nov 2025 11:50 Actions
1405 Project progress work New Normal [Coding] Manage target Phattarapong Kammee 0.00 11 Sep 2025 10:49 Actions
1404 Project progress work New Normal [Coding] Manage peak rate Phattarapong Kammee 0.00 11 Sep 2025 10:49 Actions
1403 Project progress work New Normal [Coding] Analysis Phattarapong Kammee 0.00 05 Nov 2025 11:33 Actions
1402 Project progress work New Normal [Coding] Production monitoring Phattarapong Kammee 0.00 05 Nov 2025 11:33 Actions
1401 Project progress work New Normal [Coding] Manage meter Phattarapong Kammee 0.00 05 Nov 2025 11:33 Actions