Project

General

Profile

Actions

For internal project work assignment report without Nozaki

Apply Clear

Estimated time: 20816.00 Spent time: 6215.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
167 Project progress work New Normal IoT monitoring at web screen development follow and design DB Nattapol Poeam 20.00 0.00 04 May 2024 17:20 Actions
722 Sales support In Progress Normal MCCT Make concept and summary cost Nattapol Poeam 50.00 8.00 16 Sep 2024 16:57 Actions
732 Sales support In Progress Normal [ Make concept & Summary cost ] Line operation monitoring Nattapol Poeam 50.00 4.00 25 Sep 2024 17:52 Actions
730 Sales support In Progress Normal [ Make concept & Summary cost ] Utility control monitoring and Production monitoring system Nattapol Poeam 50.00 28.00 23 Sep 2024 12:00 Actions
719 Sales support In Progress Normal Traceability new line for ADVICS Nattapol Poeam 100.00 48.00 16 Sep 2024 16:51 Actions
718 Project progress work In Progress Normal Machine operation monitoring for KAWASAKI Nattapol Poeam 100.00 56.00 16 Sep 2024 16:57 Actions
862 Project progress work In Progress Normal AHT CNC Montoring system Nattapol Poeam 60.00 16.00 24 Dec 2024 14:03 Actions
644 Project progress work In Progress Normal [ Task ] Internal management Nattapol Poeam 1000.00 44.00 11 Jul 2024 20:36 Actions
515 Project progress work New Normal Nattapol Poeam Taking Day off January-December 2024 Nattapol Poeam 80.00 104.00 04 May 2024 17:22 Actions
444 Sales support In Progress Normal For internal meeting and other Nattapol Poeam 1000.00 43.00 04 May 2024 17:22 Actions
1050 Project progress work New Normal [Coding] Nattapol Poeam 0.00 06 Aug 2025 11:37 Actions
1298 Project progress work New Normal [Requirement definition] Nattapol Poeam 64.00 0.00 04 Sep 2025 14:42 Actions
3341 Parent project In Progress Normal [PJ250103] MOC packing system for AHT modification fee Convert to picking list Nattapol Poeam 128.00 0.00 16 Jan 2026 10:43 Actions
3394 Project progress work New Normal [Requirement definition] Nattapol Poeam 80.00 0.00 17 Jan 2026 13:48 Actions
1289 Parent project In Progress Normal [PJ250052] Infrastructure IoT system for NTN Manufacturing(Thailand) NTPT Nattapol Poeam 376.00 64.00 22 Jan 2026 10:44 Actions
3043 Parent project In Progress Normal [PJ250094] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD. Nattapol Poeam 320.00 0.00 11 Mar 2026 11:13 Actions
1051 Project progress work New Normal [Installation&On-site support] Nattapol Poeam 16.00 0.00 12 Mar 2026 11:47 Actions
1047 Parent project In Progress Normal [PJ250025] Pokayoke inspection system for SIAM NITERRA Co., Ltd. Nattapol Poeam 16.00 0.00 12 Mar 2026 11:47 Actions
2996 Parent project In Progress Normal [PJ250088] MOC IoT system for wiring work AHT Nattapol Poeam 960.00 0.00 11 Mar 2026 10:44 Actions
4458 Parent project In Progress Normal [PJ260006] Camera system Preventive maintenance for STV Nattapol Poeam 160.00 0.00 05 Mar 2026 15:48 Actions
2725 Project progress work New Normal [Coding] Nattapol Poeam 88.00 0.00 18 Feb 2026 13:38 Actions
2722 Parent project In Progress Normal [PJ250068] IoT system for THAI ASAHI DENSO CO., LTD additional cost Nattapol Poeam 88.00 0.00 18 Feb 2026 13:38 Actions
1099 Project progress work New Normal [Installation&On-site support] Nattapol Poeam 16.00 0.00 19 Feb 2026 10:32 Actions
698 Parent project New Normal [PJ240025] Install Andon system for monitoring RP-EPS1 #1 PLC plan Nattapol Poeam 426.00 524.50 19 Feb 2026 10:32 Actions
6731 Parent project In Progress Normal [PJ260035] Traceability system for TOYO ADVANCED Nattapol Poeam 8.00 0.00 18 Mar 2026 10:33 Actions
(301-325/557) Per page: 25, 50, 100