Project

General

Profile

Actions

Parent project #3347

open

[PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase02

Added by Siriwilai Chaiwattanaphon 3 months ago. Updated 2 days ago.

Status:
In Progress
Priority:
Normal
Start date:
15 Dec 2025
Due date:
03 May 2026 (Due in 43 days)

Subtasks 20 (7 open13 closed)

Project progress work #4353: [Requirement definition]NewNattapol Poeam15 Dec 202503 May 2026

Actions
Project progress work #6635: [Requirement definition] Received POClosedNattapol Poeam15 Dec 202528 Dec 2025

Actions
Project progress work #6636: [Requirement definition] Internal meetingClosedNattapol Poeam12 Jan 202625 Jan 2026

Actions
Project progress work #6637: [Requirement definition] Kick-off meetingClosedNattapol Poeam09 Feb 202615 Feb 2026

Actions
Project progress work #6638: [Requirement definition] Requirements confirmationClosedNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6639: [Requirement definition] Software developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Project progress work #6640: [Requirement definition] Software service application developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Project progress work #4354: [Internal Design]NewNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6641: [Internal design] System DesignNewNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6675: [Internal design] Purchase Requisition of Server and accessory (wait supplier)ClosedPhatthadon Inthachot13 Jan 202623 Jan 2026

Actions
Project progress work #6676: [Internal design] Rack layout and SCHClosedPhatthadon Inthachot17 Jan 202621 Jan 2026

Actions
Project progress work #4355: [Coding]NewNattapol Poeam02 Mar 202618 Mar 2026

Actions
Project progress work #6928: [Coding] Setup code base for webClosedDoan Trong Hieu02 Mar 202603 Mar 2026

Actions
Project progress work #6961: [Coding] Update Dashboard UIClosedDoan Trong Hieu04 Mar 202614 Mar 2026

Actions
Project progress work #6962: [Coding] Fix PHP version issuesClosedDoan Trong Hieu16 Mar 202616 Mar 2026

Actions
Project progress work #7006: [Coding] Creat Test Scenario for Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #7008: [Coding] Creat sharepoint for tag issue Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #4356: [Installation&On-site support]NewNattapol Poeam21 Jan 202616 Mar 2026

Actions
Project progress work #6677: [Installation&On-site support] Prepare unifrom for working at on-site unimicronClosedPhatthadon Inthachot21 Jan 202621 Jan 2026

Actions
Project progress work #6990: [Installation&On-site support] Assy and wiring setup PC serverClosedPhatthadon Inthachot16 Mar 202616 Mar 2026

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 3 months ago

1. Software
1.1 Software development fee 1 job

2. Internal Installation
2.1 Drawing design 1 job
2.2 Assembly 1 job
2.3 Wiring 1 job

3. Installation
3.1 Program installation 1 job
3.2 Program I/O Check and data machine collection 1 job
3

.3 Program test 1 job
3.4 Program commissioning 1 job

Note)
Program modification costs to equipment manufacturers are not included.
Wiring and power supply costs are not included.
PLC and Sensor not included
Phase01: 300 pieces, Phase02: 500 pieces
Phase 01: 300 installations in 6-7 months
Phase 02: 500 installations in 2-3 months

Actions #2

Updated by Siriwilai Chaiwattanaphon 2 months ago

  • Subject changed from [PJ250010X] IoT system for Unimicron(Thailand)Co., Ltd Phase02 to [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase02
Actions

Also available in: Atom PDF