Project

General

Profile

Actions

Parent project #3347

open

[PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase02

Added by Siriwilai Chaiwattanaphon 5 months ago. Updated 5 days ago.

Status:
In Progress
Priority:
Normal
Start date:
15 Dec 2025
Due date:
03 May 2026 (2 days late)

Subtasks 29 (7 open22 closed)

Project progress work #4353: [Requirement definition]NewNattapol Poeam15 Dec 202503 May 2026

Actions
Project progress work #6635: [Requirement definition] Received POClosedNattapol Poeam15 Dec 202528 Dec 2025

Actions
Project progress work #6636: [Requirement definition] Internal meetingClosedNattapol Poeam12 Jan 202625 Jan 2026

Actions
Project progress work #6637: [Requirement definition] Kick-off meetingClosedNattapol Poeam09 Feb 202615 Feb 2026

Actions
Project progress work #6638: [Requirement definition] Requirements confirmationClosedNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6639: [Requirement definition] Software developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Project progress work #6640: [Requirement definition] Software service application developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Project progress work #7128: [Requirement definition] 'Safety trainingClosedWorawit Khantamool07 Apr 202607 Apr 2026

Actions
Project progress work #4354: [Internal Design]NewNattapol Poeam12 Jan 202601 Apr 2026

Actions
Project progress work #6641: [Internal design] System DesignNewNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6675: [Internal design] Purchase Requisition of Server and accessory (wait supplier)ClosedPhatthadon Inthachot13 Jan 202623 Jan 2026

Actions
Project progress work #6676: [Internal design] Rack layout and SCHClosedPhatthadon Inthachot17 Jan 202621 Jan 2026

Actions
Project progress work #7194: [Internal Design] Order Sw. HubClosedPhatthadon Inthachot30 Mar 202601 Apr 2026

Actions
Project progress work #4355: [Coding]NewNattapol Poeam02 Mar 202630 Apr 2026

Actions
Project progress work #6928: [Coding] Setup code base for webClosedDoan Trong Hieu02 Mar 202603 Mar 2026

Actions
Project progress work #6961: [Coding] Update Dashboard UIClosedDoan Trong Hieu04 Mar 202614 Mar 2026

Actions
Project progress work #6962: [Coding] Fix PHP version issuesClosedDoan Trong Hieu16 Mar 202616 Mar 2026

Actions
Project progress work #7006: [Coding] Creat Test Scenario for Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #7008: [Coding] Creat sharepoint for tag issue Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #7321: [Coding] Creat Test Scenario for Test API Unimicron projectClosedMekkalar Sansiri27 Apr 202628 Apr 2026

Actions
Project progress work #7334: [Coding] Implement api Flow Summary dashboardClosedNopparat Talalux10 Apr 202611 Apr 2026

Actions
Project progress work #7335: [Coding] Implement api meter compareClosedNopparat Talalux16 Apr 202616 Apr 2026

Actions
Project progress work #7337: [Coding] Implement api Web UnimicronClosedNopparat Talalux20 Apr 202630 Apr 2026

Actions
Project progress work #4356: [Installation&On-site support]NewNattapol Poeam21 Jan 202609 Apr 2026

Actions
Project progress work #6677: [Installation&On-site support] Prepare unifrom for working at on-site unimicronClosedPhatthadon Inthachot21 Jan 202621 Jan 2026

Actions
Project progress work #6990: [Installation&On-site support] Assy and wiring setup PC serverClosedPhatthadon Inthachot16 Mar 202616 Mar 2026

Actions
Project progress work #7189: [Installation&On-site support] Safety trainning ClosedNattapong Sukcharoen07 Apr 202607 Apr 2026

Actions
Project progress work #7196: [Installation&On-site support] Install serverClosedPhatthadon Inthachot09 Apr 202609 Apr 2026

Actions
Project progress work #7197: [Installation&On-site support] Safety TrainingClosedPhatthadon Inthachot24 Mar 202624 Mar 2026

Actions
Actions

Also available in: Atom PDF