[PJ260075] Production management system for NIPPN (Thailand) Co.,Ltd. Feb 2026

Added by Waraporn Promsopa 3 months ago. Updated about 1 month ago.

Status:
In Progress
Priority:
Normal
Start date:
30 Apr 2026
Due date:
15 Jun 2026 (40 days late)

Subtasks 13 (1 open12 closed)

Project progress work #7322: [Requirement definition] Meeting On siteClosedMekkalar Sansiri30 Apr 202630 Apr 2026

Actions
Project progress work #8616: [Coding]New15 Jun 202615 Jun 2026

Actions
Project progress work #8617: [Coding] Add Scraps Management Menu and sub menu tree Scraps Order and Scraps Item MasterClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8618: [Coding] Add Scraps Order list from sale documents and start and end date range filter and CSV exportClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8619: [Coding] Add Order modal with editable item grid and Add Row and Delete Row and seller NIPPN or NFT toggle routing line totalsClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8620: [Coding] Add Save new order that inserts header and lines in one transaction and computes total amount and total weight with validationsClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8621: [Coding] Add View Order Details read only table with per seller Sales and grand Sales TotalClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8622: [Coding] Add Edit Order modal updating Invoice No and Sale Scrap with validationsClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8623: [Coding] Add Cancel selected orders that hard deletes header and lines with confirmationClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8624: [Coding] Add Excel export of order from template with item rows and seller totals and weight sumClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8625: [Coding] Add Scraps Item Master list joining scrap items to units with Item Name filter and CSV exportClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8626: [Coding] Add new scrap item that inserts item and unit in one transaction with auto generated Item Code with validationsClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Project progress work #8627: [Coding] Add soft delete selected scrap items with confirmationClosedNatthakit Saengrungrat15 Jun 202615 Jun 2026

Actions
Actions #1

Updated by Waraporn Promsopa 3 months ago

1 Software
1-1 Senior engineer A development + installation work 1 month
1-2 Middle engineer B development + installation work 1 month
1-3 Middle engineer C development + installation work 1 month

Period : Period: March 5,2026 to April 4,2026

Senior engineer A development Working Days : 7/19 days
Base monthly salary 160,000 Baht, 19 working*7 days
Middle engineer B development Working Days :12/19 days
Base monthly salary 140,000 Baht, 19 working days*12 days
Middle engineer C development Working Days : 13/19 days
Base monthly salary 140,000 Baht, 19 working days*13 days

Additional Development Work-Billing Conditions
1.Work Arrangement
The additional development work shall be conducted under a Time & Material basis
The total service fee shall be calculated based on the actual working days of assigned
engineers multiplied by the agreed daily rate.
2.Definition of Working Day
Working time shall be calculated as follows:
5 hours or more of work: counted as 1 full working day
Less than 5 hours of work: counted as 0.5 working day
The following activities shall be considered as billable working time:
Software development
System testing
Investigation and troubleshooting
Customer inquiries and support
Specification confirmation and adjustments
Meetings and discussions
Documentation preparation
Debugging and system verification
3.Reporting
The service provider will send a quotation detailing the working days of each engine
Unless any objection is raised within five (5) business days,
the report shall be deemed accepted by the customer.

Actions #2

Updated by Waraporn Promsopa 3 months ago

  • Status changed from In Progress to Closed
Actions #3

Updated by Waraporn Promsopa 3 months ago

  • Status changed from Closed to In Progress
Actions