Parent project #3346

open

[PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase01

Added by Siriwilai Chaiwattanaphon 3 months ago. Updated 4 days ago.

Status:
In Progress
Priority:
Normal
Start date:
15 Dec 2025
Due date:
24 May 2026 (Due in about 2 months)

Subtasks 21 (9 open12 closed)

Project progress work #4349: [Requirement definition]In ProgressNattapol Poeam15 Dec 202503 May 2026

Actions
Project progress work #6618: [Requirement definition] Received POClosedNattapol Poeam15 Dec 202518 Dec 2025

Actions
Project progress work #6619: [Requirement definition] Internal meetingClosedNattapol Poeam12 Jan 202625 Jan 2026

Actions
Project progress work #6620: [Requirement definition] Kick-off meetingClosedNattapol Poeam09 Feb 202615 Feb 2026

Actions
Project progress work #6621: [Requirement definition] Requirements confirmationClosedNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6623: [Requirement definition] Software developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Project progress work #4350: [Internal Design]NewNattapol Poeam11 Jan 202608 Mar 2026

Actions
Project progress work #6622: [Internal design] System DesignNewNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6679: [Internal design] Rack layout and SCHClosedPhatthadon Inthachot11 Jan 202627 Jan 2026

Actions
Project progress work #6680: [Internal design] Purchase Requisition of Server and accessory (wait supplier)ClosedPhatthadon Inthachot13 Jan 202623 Jan 2026

Actions
Project progress work #4351: [Coding]NewNattapol Poeam02 Mar 202618 Mar 2026

Actions
Project progress work #6929: [Coding] Setup code base for webClosedDoan Trong Hieu02 Mar 202603 Mar 2026

Actions
Project progress work #6959: [Coding] Update Dashboard UIClosedDoan Trong Hieu04 Mar 202614 Mar 2026

Actions
Project progress work #6960: [Coding] Fix PHP version issuesClosedDoan Trong Hieu16 Mar 202616 Mar 2026

Actions
Project progress work #7007: [Coding] Creat Test Scenario for Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #7009: [Coding] Creat sharepoint for tag issue Unimicron projectClosedMekkalar Sansiri16 Mar 202618 Mar 2026

Actions
Project progress work #4352: [Installation&On-site support]NewNattapol Poeam21 Jan 202624 May 2026

Actions
Project progress work #6624: [Installation&On-site support] Hardware server installationNewNattapol Poeam06 Apr 202612 Apr 2026

Actions
Project progress work #6625: [Installation&On-site support] Hardware configurationNewNattapol Poeam06 Apr 202603 May 2026

Actions
Project progress work #6626: [Installation&On-site support] Software installationNewNattapol Poeam04 May 202624 May 2026

Actions
Project progress work #6678: [Installation&On-site support] Prepare unifrom for working at on-site unimicronClosedPhatthadon Inthachot21 Jan 202621 Jan 2026

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 2 months ago

  • Subject changed from [PJ250010X] IoT system for Unimicron(Thailand)Co., Ltd Phase01 to [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase01

Flow meter monitoring system quote for Thailand factory /

1. Software
1.1 Software development fee

2. Hardware
2.1 RACK server ( Server room ) 1 set
2.2 DELL EMC PowerEdge R760xs 1 set
2.3 DELL EMC Microsoft Windows Server 2025 Standard ROK 16 Core 1 set
2.4 APC Easy UPS On-Line SRV RM 1 set
2.5 DELL Monitor Essential E2225HM 1 set
2.6 Microsoft SQL Server 2022 Standard Edition 1 set
2.7 SQL Server 2022 - 1 User CAL Commercial 50 set
2.8 OKER VGA Cable 3 meter 1 set
2.9 DELL 960GB SSD SATA Read Intensive 6Gbps 512e 2.5in Hot-Plug, S4520, 5 set

3. Internal Installation
3.1 Drawing design 1 job
3.2 Assembly 1 job
3.3 Wiring 1 job

4. Installation
4.1 Program installation 1 job
4.2 Program I/O Check and data machine collection 1 job
4.3 Program test 1 job
4.4 Program commissioning 1 job

Note )
  • Program modification costs to equipment manufacturers are not included.
  • Wiring and power supply costs are not included.
  • PLC and Sensor not included
  • Phase01: 300 pieces, Phase02: 500 pieces
  • Phase 01: 300 installations in 6-7 months
  • Phase 02: 500 installations in 2-3 months