Project

General

Profile

Actions

Project progress work #4350

open

Parent project #3346: [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase01

[Internal Design]

Added by Siriwilai Chaiwattanaphon 2 months ago. Updated about 1 month ago.

Status:
New
Priority:
Normal
Start date:
11 Jan 2026
Due date:
08 Mar 2026 (13 days late)
% Done:

84%

Estimated time:
(Total: 576.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 3 (1 open2 closed)

Project progress work #6622: [Internal design] System DesignNewNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6679: [Internal design] Rack layout and SCHClosedPhatthadon Inthachot11 Jan 202627 Jan 2026

Actions
Project progress work #6680: [Internal design] Purchase Requisition of Server and accessory (wait supplier)ClosedPhatthadon Inthachot13 Jan 202623 Jan 2026

Actions

No data to display

Actions

Also available in: Atom PDF