49

30

SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3303: [Internal Design] Project progress work #3303: [Internal Design]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 03 Nov 2025
Due date: 30 Nov 2025
Assignee:
Priority: Normal

1

AH BRAKE (THAILAND) CO., LTD. - Project progress work #4439: [Installation&On-site support] Project progress work #4439: [Installation&On-site support]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Parent project #2996: [PJ250088] MOC IoT system f... Parent project #2996: [PJ250088] MOC IoT system for wiring work AHT

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2934: [Installation&On-site suppo... Project progress work #2934: [Installation&On-site support] UAT

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 01 Dec 2025
Due date: 18 Jan 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2901: [Coding] Software development Project progress work #2901: [Coding] Software development

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 08 Feb 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2899: [Internal Design] Software ... Project progress work #2899: [Internal Design] Software system design

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #2810: [Coding] Master PLC Project progress work #2810: [Coding] Master PLC

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 01 Dec 2025
Due date: 20 Feb 2026
Assignee: Sermsak Prowee
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #1035: [Coding] Project progress work #1035: [Coding]

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 08 Feb 2026
Assignee: Anek Sanohkham
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #1034: [Internal Design] Project progress work #1034: [Internal Design]

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee: Anek Sanohkham
Priority: Normal

2

A.N.I. LOGISTICS, LTD. - Project progress work #3054: [Coding] Handy UI Script Project progress work #3054: [Coding] Handy UI Script

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2025
Due date: 02 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

3

4

A.N.I. LOGISTICS, LTD. - Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3135: [Coding] Reprint Case mark ... Project progress work #3135: [Coding] Reprint Case mark document

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 04 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

5

A.N.I. LOGISTICS, LTD. - Project progress work #3101: [Coding] Web Development Project progress work #3101: [Coding] Web Development

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 26 Jun 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3343: [Internal Design] Project progress work #3343: [Internal Design]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3342: [Requirement definition] Project progress work #3342: [Requirement definition]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Parent project #3341: [PJ250103] MOC packing syst... Parent project #3341: [PJ250103] MOC packing system for AHT modification fee Convert to picking list

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Dec 2025
Due date: 23 Dec 2025
Assignee: Nattapol Poeam
Priority: Normal

6

50

7

8

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3253: [Coding] Show Classify Lot ... Project progress work #3253: [Coding] Show Classify Lot (Barcode 39)

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Dec 2025
Due date: 08 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3208: [Coding] Mechanical Project progress work #3208: [Coding] Mechanical

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 11 Nov 2025
Due date: 08 Dec 2025
Assignee: Nattawat Hannok
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3344: [Coding] Project progress work #3344: [Coding]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 08 Dec 2025
Due date: 17 Dec 2025
Assignee:
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3252: [Coding] Process Control sy... Project progress work #3252: [Coding] Process Control system

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Dec 2025
Due date: 09 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3251: [Coding] Project progress work #3251: [Coding]

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Dec 2025
Due date: 16 Mar 2026
Assignee: Soraya Norasing
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2932: [Installation&On-site suppo... Project progress work #2932: [Installation&On-site support] SIT Production system

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 08 Dec 2025
Due date: 23 Jan 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2900: [Internal Design] Hardware ... Project progress work #2900: [Internal Design] Hardware system design

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 08 Dec 2025
Due date: 13 Dec 2025
Assignee:
Priority: Normal

9

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3254: [Coding] History Page Project progress work #3254: [Coding] History Page

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 09 Dec 2025
Due date: 11 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #1287: [Coding] Web application Project progress work #1287: [Coding] Web application

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 09 Dec 2025
Due date: 13 Feb 2026
Assignee: Worawit Khantamool
Priority: Normal

10

THAI MATTO NS CO., LTD. - Project progress work #1594: [Coding] i-Reporter develop... Project progress work #1594: [Coding] i-Reporter development

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 10 Dec 2025
Due date: 10 Dec 2025
Assignee: Arunwit Isarapongporn
Priority: Normal

11

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3254: [Coding] History Page Project progress work #3254: [Coding] History Page

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 09 Dec 2025
Due date: 11 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1587: [Coding] Weighing API Project progress work #1587: [Coding] Weighing API

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 16 Oct 2025
Due date: 11 Dec 2025
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #6478: [Coding] WS client Project progress work #6478: [Coding] WS client

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 11 Dec 2025
Due date: 16 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal

12

AH BRAKE (THAILAND) CO., LTD. - Project progress work #3343: [Internal Design] Project progress work #3343: [Internal Design]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3342: [Requirement definition] Project progress work #3342: [Requirement definition]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3215: [Coding] Power on & I/O Check Project progress work #3215: [Coding] Power on & I/O Check

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Dec 2025
Due date: 12 Dec 2025
Assignee: Taweesak Suriyon
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3207: [Coding] Electrical Project progress work #3207: [Coding] Electrical

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 11 Nov 2025
Due date: 12 Dec 2025
Assignee: Taweesak Suriyon
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3255: [Coding] Classify Process S... Project progress work #3255: [Coding] Classify Process Support Direct Taping Machine

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Dec 2025
Due date: 18 Dec 2025
Assignee: Soraya Norasing
Priority: Normal

13

SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3329: [Installation&On-site suppo... Project progress work #3329: [Installation&On-site support] Line 5: Installation / Wiring / Config / IO Check

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 13 Dec 2025
Due date: 13 Dec 2025
Assignee: Konlawat Saechee
Priority: Normal
SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3328: [Installation&On-site suppo... Project progress work #3328: [Installation&On-site support] Line 4: Installation / Wiring / Config / IO Check

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 13 Dec 2025
Due date: 13 Dec 2025
Assignee: Konlawat Saechee
Priority: Normal
SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3327: [Installation&On-site suppo... Project progress work #3327: [Installation&On-site support] Line 3: Installation / Wiring / Config / IO Check

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 13 Dec 2025
Due date: 13 Dec 2025
Assignee: Konlawat Saechee
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2900: [Internal Design] Hardware ... Project progress work #2900: [Internal Design] Hardware system design

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 08 Dec 2025
Due date: 13 Dec 2025
Assignee:
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3388: [Installation&On-site suppo... Project progress work #3388: [Installation&On-site support] WS controller installation

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 13 Dec 2025
Due date: 26 Dec 2025
Assignee: Konlawat Saechee
Priority: Normal
NKT NIPPON KONPO (THAILAND) CO., LTD - Parent project #3246: [PJ2500XX] Modification WMS... Parent project #3246: [PJ2500XX] Modification WMS function

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: In Progress
Start date: 13 Dec 2025
Due date:
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3222: [Installation&On-site support] Project progress work #3222: [Installation&On-site support]

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 13 Dec 2025
Due date: 05 Mar 2026
Assignee:
Priority: Normal
51

14

THAI MATTO NS CO., LTD. - Project progress work #6479: [Coding] Blender Pokayoke Project progress work #6479: [Coding] Blender Pokayoke

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 14 Dec 2025
Due date: 12 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal

15

THAI ASAHI DENSO CO., LTD. - Problem-Bug #4400: [Issue] Problem-Bug #4400: [Issue]

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 15 Dec 2025
Due date: 14 Jan 2026
Assignee: Worawit Khantamool
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4353: [Requirement definition] Project progress work #4353: [Requirement definition]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 15 Dec 2025
Due date: 03 May 2026
Assignee: Nattapol Poeam
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4349: [Requirement definition] Project progress work #4349: [Requirement definition]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: In Progress
Start date: 15 Dec 2025
Due date: 03 May 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3386: [Coding] WH/Picking Plan(Ot... Project progress work #3386: [Coding] WH/Picking Plan(Others) FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 15 Dec 2025
Due date: 14 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3385: [Coding] WH/Picking Plan(Pa... Project progress work #3385: [Coding] WH/Picking Plan(Packaging) FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 15 Dec 2025
Due date: 14 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3384: [Coding] WH/Picking Plan(Pi... Project progress work #3384: [Coding] WH/Picking Plan(Pigment/Additive) FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 15 Dec 2025
Due date: 14 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3383: [Coding] WH/Picking Plan(Re... Project progress work #3383: [Coding] WH/Picking Plan(Resin) FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 15 Dec 2025
Due date: 14 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Parent project #3347: [PJ2500104] IoT system for ... Parent project #3347: [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase02

Project: UNIMICRON (THAILAND) CO., LTD.
Status: In Progress
Start date: 15 Dec 2025
Due date: 03 May 2026
Assignee: Nattapol Poeam
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Parent project #3346: [PJ2500104] IoT system for ... Parent project #3346: [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase01

Project: UNIMICRON (THAILAND) CO., LTD.
Status: In Progress
Start date: 15 Dec 2025
Due date: 24 May 2026
Assignee: Nattapol Poeam
Priority: Normal

16

ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. - Project progress work #3003: [Internal Design] Project progress work #3003: [Internal Design]

Project: ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD.
Status: New
Start date: 17 Nov 2025
Due date: 16 Dec 2025
Assignee: Anek Sanohkham
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3381: [Coding] Color matching Bac... Project progress work #3381: [Coding] Color matching Backend

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 16 Dec 2025
Due date: 20 Feb 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3380: [Coding] Color matching Fro... Project progress work #3380: [Coding] Color matching Frontend

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 16 Dec 2025
Due date: 20 Feb 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal
NTPT COMPANY LIMITED. - Project progress work #1304: [Installation&On-site support] Project progress work #1304: [Installation&On-site support]

Project: NTPT COMPANY LIMITED.
Status: New
Start date: 16 Dec 2025
Due date: 19 Jan 2026
Assignee:
Priority: Normal

17

A.N.I. LOGISTICS, LTD. - Project progress work #3373: [Installation&On-site suppo... Project progress work #3373: [Installation&On-site support] Pre-Go live for 1line

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 17 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3344: [Coding] Project progress work #3344: [Coding]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 08 Dec 2025
Due date: 17 Dec 2025
Assignee:
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3375: [Installation&Onsite suppor... Project progress work #3375: [Installation&Onsite support] Monitoring program install

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3374: [Installation&Onsite suppor... Project progress work #3374: [Installation&Onsite support] On-line program modification

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal

18

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3255: [Coding] Classify Process S... Project progress work #3255: [Coding] Classify Process Support Direct Taping Machine

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Dec 2025
Due date: 18 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1706: [Coding] Dashboard report –... Project progress work #1706: [Coding] Dashboard report – Production monitoring

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 11 Nov 2025
Due date: 18 Dec 2025
Assignee: Thiraporn Amornsirinukorh
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3345: [Installation&On-site support] Project progress work #3345: [Installation&On-site support]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 18 Dec 2025
Due date: 23 Dec 2025
Assignee:
Priority: Normal

19

A.N.I. LOGISTICS, LTD. - Project progress work #3375: [Installation&Onsite suppor... Project progress work #3375: [Installation&Onsite support] Monitoring program install

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3374: [Installation&Onsite suppor... Project progress work #3374: [Installation&Onsite support] On-line program modification

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Dec 2025
Due date: 19 Dec 2025
Assignee:
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3256: [Coding] AG AOI Project progress work #3256: [Coding] AG AOI

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 19 Dec 2025
Due date: 25 Dec 2025
Assignee: Soraya Norasing
Priority: Normal

20

NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #6546: [Internal design] Dwg. Desi... Project progress work #6546: [Internal design] Dwg. Design & Installation

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: In Progress
Start date: 20 Dec 2025
Due date: 30 Apr 2026
Assignee: Taweesak Suriyon
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #3395: [Internal Design] Project progress work #3395: [Internal Design]

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 20 Dec 2025
Due date: 30 Apr 2026
Assignee: Nattapol Poeam
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Parent project #3390: [PJ2500107] Traceability sy... Parent project #3390: [PJ2500107] Traceability system for NTMT RFID concept

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: In Progress
Start date: 20 Dec 2025
Due date: 30 Apr 2026
Assignee: Nattapol Poeam
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #2816: [Installation&On-site support] Project progress work #2816: [Installation&On-site support]

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 20 Dec 2025
Due date: 05 Mar 2026
Assignee:
Priority: Normal
52

21

22

A.N.I. LOGISTICS, LTD. - Project progress work #3365: [Installation&On-site suppo... Project progress work #3365: [Installation&On-site support] User Testing & Trial (WC)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 22 Dec 2025
Due date: 26 Dec 2025
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Parent project #3336: [PJ250102] Web EDI system c... Parent project #3336: [PJ250102] Web EDI system customize Request label print of Nov.2025

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: In Progress
Start date: 22 Dec 2025
Due date: 25 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2953: [Installation&On-site suppo... Project progress work #2953: [Installation&On-site support] Production monitoring system UAT

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 22 Dec 2025
Due date: 18 Jan 2026
Assignee: Nattapong Sukcharoen
Priority: Normal

23

AH BRAKE (THAILAND) CO., LTD. - Project progress work #3345: [Installation&On-site support] Project progress work #3345: [Installation&On-site support]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 18 Dec 2025
Due date: 23 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Parent project #3341: [PJ250103] MOC packing syst... Parent project #3341: [PJ250103] MOC packing system for AHT modification fee Convert to picking list

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Dec 2025
Due date: 23 Dec 2025
Assignee: Nattapol Poeam
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3378: [Coding] Outbound Schedule ... Project progress work #3378: [Coding] Outbound Schedule Detail FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 23 Dec 2025
Due date: 25 Dec 2025
Assignee: Lux Aubon
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3377: [Codin] Inbound Schedule De... Project progress work #3377: [Codin] Inbound Schedule Detail Fix

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 23 Dec 2025
Due date: 25 Dec 2025
Assignee: Lux Aubon
Priority: Normal

24

THAI MATTO NS CO., LTD. - Project progress work #3387: [Coding] Process control Project progress work #3387: [Coding] Process control

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 24 Dec 2025
Due date: 26 Dec 2025
Assignee: Surat Duangchiaw
Priority: Normal

25

THAI MATTO NS CO., LTD. - Project progress work #3378: [Coding] Outbound Schedule ... Project progress work #3378: [Coding] Outbound Schedule Detail FIX

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 23 Dec 2025
Due date: 25 Dec 2025
Assignee: Lux Aubon
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3377: [Codin] Inbound Schedule De... Project progress work #3377: [Codin] Inbound Schedule Detail Fix

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 23 Dec 2025
Due date: 25 Dec 2025
Assignee: Lux Aubon
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3364: [Installation&On-site suppo... Project progress work #3364: [Installation&On-site support] SD card installation 8units

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 25 Dec 2025
Due date: 25 Dec 2025
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Parent project #3336: [PJ250102] Web EDI system c... Parent project #3336: [PJ250102] Web EDI system customize Request label print of Nov.2025

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: In Progress
Start date: 22 Dec 2025
Due date: 25 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3256: [Coding] AG AOI Project progress work #3256: [Coding] AG AOI

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 19 Dec 2025
Due date: 25 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #6543: [Installation&On-site suppo... Project progress work #6543: [Installation&On-site support] Design & Installation Line WA640

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: In Progress
Start date: 25 Dec 2025
Due date: 31 Jan 2026
Assignee: Taweesak Suriyon
Priority: Normal
SHINDENGEN INDONESIA - Project progress work #4414: [Installation&On-site support] Project progress work #4414: [Installation&On-site support]

Project: SHINDENGEN INDONESIA
Status: New
Start date: 25 Dec 2025
Due date: 19 Jan 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal
SHINDENGEN INDONESIA - Project progress work #2763: [Installation&On-site support] Project progress work #2763: [Installation&On-site support]

Project: SHINDENGEN INDONESIA
Status: New
Start date: 25 Dec 2025
Due date: 10 Apr 2026
Assignee:
Priority: Normal
SHINDENGEN INDONESIA - Project progress work #2762: [Coding] Project progress work #2762: [Coding]

Project: SHINDENGEN INDONESIA
Status: New
Start date: 25 Dec 2025
Due date: 18 Jan 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal

26

THAI MATTO NS CO., LTD. - Project progress work #3388: [Installation&On-site suppo... Project progress work #3388: [Installation&On-site support] WS controller installation

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 13 Dec 2025
Due date: 26 Dec 2025
Assignee: Konlawat Saechee
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3387: [Coding] Process control Project progress work #3387: [Coding] Process control

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 24 Dec 2025
Due date: 26 Dec 2025
Assignee: Surat Duangchiaw
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3365: [Installation&On-site suppo... Project progress work #3365: [Installation&On-site support] User Testing & Trial (WC)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 22 Dec 2025
Due date: 26 Dec 2025
Assignee:
Priority: Normal
PROSPIRA THAILAND CO., LTD. - Project progress work #3350: [Installation&On-site suppo... Project progress work #3350: [Installation&On-site support] Onsite support issue and request

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 14 Oct 2025
Due date: 26 Dec 2025
Assignee: Phongphan Suwanteamee
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3148: [Installation&On-site support] Project progress work #3148: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Sep 2025
Due date: 26 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
PROSPIRA THAILAND CO., LTD. - Project progress work #3147: [Installation&OIn-site supp... Project progress work #3147: [Installation&OIn-site support] Onsite support

Project: PROSPIRA THAILAND CO., LTD.
Status: In Progress
Start date: 14 Oct 2025
Due date: 26 Dec 2025
Assignee: Kittikun Chunhachotwanit
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #3340: [Installation&On-site support] Project progress work #3340: [Installation&On-site support]

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: In Progress
Start date: 26 Dec 2025
Due date:
Assignee: Nattaporn Chaiya
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3257: [Coding] Check Machine Status Project progress work #3257: [Coding] Check Machine Status

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 26 Dec 2025
Due date: 27 Dec 2025
Assignee: Soraya Norasing
Priority: Normal

27

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3257: [Coding] Check Machine Status Project progress work #3257: [Coding] Check Machine Status

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 26 Dec 2025
Due date: 27 Dec 2025
Assignee: Soraya Norasing
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3142: [Installation&Onsite support] Project progress work #3142: [Installation&Onsite support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Nov 2025
Due date: 27 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
1

28

THAI ASAHI DENSO CO., LTD. - Project progress work #2933: [Installation&On-site suppo... Project progress work #2933: [Installation&On-site support] SIT Utility system

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 28 Dec 2025
Assignee:
Priority: Normal

29

30

31

1

2

3