Project

General

Profile

Actions

Project progress work #2933

closed

Parent project #1284: [PJ250039] Infrastructure IoT system for Thai Asahi Denso

Project progress work #1288: [Installation&On-site support] Software installation

[Installation&On-site support] SIT Utility system

Added by Siriwilai Chaiwattanaphon 3 months ago. Updated 18 days ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Start date:
24 Nov 2025
Due date:
28 Dec 2025
% Done:

100%

Estimated time:
(Total: 40.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 3 (0 open3 closed)

Project progress work #2949: [Installation&On-site support] Utility monitoringClosedPanupong Raksakit24 Nov 202525 Nov 2025

Actions
Project progress work #2950: [Installation&On-site support] Utility data monitoringClosedPanupong Raksakit26 Nov 202527 Nov 2025

Actions
Project progress work #2951: [Installation&On-site support] Air flow monitoringClosedPanupong Raksakit28 Dec 202528 Dec 2025

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 18 days ago

  • Status changed from New to Closed
Actions

Also available in: Atom PDF