Project progress work #3207

open

Parent project #2807: [PJ250079] Traceability system for WA640

[Coding] Electrical

Added by Siriwilai Chaiwattanaphon 8 days ago. Updated 6 days ago.

Status:
New
Priority:
Normal
Start date:
11 Nov 2025
Due date:
12 Dec 2025 (7 days late)
% Done:

100%

Estimated time:
(Total: 288.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 7 (1 open6 closed)

Project progress work #3209: [Coding] Drawing DesignClosedTaweesak Suriyon11 Nov 202514 Nov 2025

Actions
Project progress work #3210: [Coding] Part listClosedTaweesak Suriyon12 Nov 202515 Nov 2025

Actions
Project progress work #3211: [Coding] PR RequestClosedTaweesak Suriyon17 Nov 202523 Nov 2025

Actions
Project progress work #3212: [Coding] Order equipmentClosedTaweesak Suriyon19 Nov 202508 Dec 2025

Actions
Project progress work #3213: [Coding] Check EquipmentClosedTaweesak Suriyon08 Dec 202509 Dec 2025

Actions
Project progress work #3214: [Coding] Assy & WiringClosedTaweesak Suriyon10 Dec 202511 Dec 2025

Actions
Project progress work #3215: [Coding] Power on & I/O CheckNewTaweesak Suriyon12 Dec 202512 Dec 2025

Actions