[PJ250079] Traceability system for WA640

Added by Siriwilai Chaiwattanaphon about 2 months ago. Updated 6 days ago.

Status:
In Progress
Priority:
Normal
Assignee:
Start date:
07 Nov 2025
Due date:
16 Jan 2026 (Due in 28 days)

Files


Subtasks 64 (52 open12 closed)

Project progress work #2808: [Requirement definition]NewNattapol Poeam07 Nov 202507 Nov 2025

Actions
Project progress work #2809: [Internal Design]New10 Nov 202522 Nov 2025

Actions
Project progress work #3205: [Internal Design] Specification design NewNattapol Poeam10 Nov 202516 Nov 2025

Actions
Project progress work #3206: [Internal Design] Backup software / Parameter / HMI MachineNewNattapong Sukcharoen22 Nov 202522 Nov 2025

Actions
Project progress work #2810: [Coding] Master PLCNewSermsak Prowee01 Dec 202511 Jan 2026

Actions
Project progress work #3185: [Coding] DevelopmentNewSermsak Prowee01 Dec 202520 Dec 2025

Actions
Project progress work #3186: [Coding] SITNewSermsak Prowee05 Jan 202611 Jan 2026

Actions
Project progress work #3187: [Coding] Windows application & DatabaseNewSuphawat Tinaso05 Jan 202611 Jan 2026

Actions
Project progress work #3188: [Coding] Development and modificationNewSuphawat Tinaso

Actions
Project progress work #3189: [Coding] SITNewSuphawat Tinaso05 Jan 202611 Jan 2026

Actions
Project progress work #3190: [Coding] Web applicationNewPhattarapong Kammee05 Jan 202611 Jan 2026

Actions
Project progress work #3191: [Coding] Development and modificationNewPhattarapong Kammee

Actions
Project progress work #3192: [Coding] SITNewPhattarapong Kammee05 Jan 202611 Jan 2026

Actions
Project progress work #3193: [Coding] Machine data prepareNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3194: [Coding] Boring machine [ Zone 1 ]NewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3195: [Coding] Bracket Welding machine [ Zone 1 ]NewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3196: [Coding] Welding No.1 machine [ Zone 1 ]NewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3197: [Coding] Welding No.2 machine [ Zone 1 ]NewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3198: [Coding] 500D Welding machine [ Zone 1 ]NewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3199: [Coding] Pump assy machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3200: [Coding] Tube Assy machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3201: [Coding] Leak test machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3202: [Coding] Guage Check machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3203: [Coding] Insulator Assy machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3204: [Coding] Final Inspection machine [ Zone 2 ]NewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3207: [Coding] ElectricalNewTaweesak Suriyon11 Nov 202512 Dec 2025

Actions
Project progress work #3209: [Coding] Drawing DesignClosedTaweesak Suriyon11 Nov 202514 Nov 2025

Actions
Project progress work #3210: [Coding] Part listClosedTaweesak Suriyon12 Nov 202515 Nov 2025

Actions
Project progress work #3211: [Coding] PR RequestClosedTaweesak Suriyon17 Nov 202523 Nov 2025

Actions
Project progress work #3212: [Coding] Order equipmentClosedTaweesak Suriyon19 Nov 202508 Dec 2025

Actions
Project progress work #3213: [Coding] Check EquipmentClosedTaweesak Suriyon08 Dec 202509 Dec 2025

Actions
Project progress work #3214: [Coding] Assy & WiringClosedTaweesak Suriyon10 Dec 202511 Dec 2025

Actions
Project progress work #3215: [Coding] Power on & I/O CheckNewTaweesak Suriyon12 Dec 202512 Dec 2025

Actions
Project progress work #3208: [Coding] MechanicalNewNattawat Hannok11 Nov 202508 Dec 2025

Actions
Project progress work #3216: [Coding] Drawing DesignClosedNattawat Hannok11 Nov 202513 Nov 2025

Actions
Project progress work #3217: [Coding] Part listClosedNattawat Hannok14 Nov 202516 Nov 2025

Actions
Project progress work #3218: [Coding] PR EquipmentClosedNattawat Hannok25 Nov 202527 Nov 2025

Actions
Project progress work #3219: [Coding] Order equipmentClosedNattawat Hannok21 Nov 202508 Dec 2025

Actions
Project progress work #3220: [Coding] Check equipmentClosedNattawat Hannok08 Dec 202508 Dec 2025

Actions
Project progress work #3221: [Coding] AssyClosedNattawat Hannok08 Dec 202508 Dec 2025

Actions
Project progress work #3222: [Installation&On-site support]New13 Dec 202516 Jan 2026

Actions
Project progress work #3223: [Installation&On-site support] Wiring and Installation EENewTaweesak Suriyon13 Dec 202514 Dec 2025

Actions
Project progress work #3224: [Installation&On-site support] Wiring and Installation MENewNattawat Hannok13 Dec 202514 Dec 2025

Actions
Project progress work #3225: [Installation&On-site support] Boring machineNewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3226: [Installation&On-site support] Bracket Welding machineNewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3227: [Installation&On-site support] Welding No.1 MachineNewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3228: [Installation&On-site support] Welding No.2 MachineNewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3229: [Installation&On-site support] 500D Welding machineNewPurinat Thongbaiyai12 Jan 202616 Jan 2026

Actions
Project progress work #3230: [Installation&On-site support] Pump assy machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3231: [Installation &On-site support] Tube Assy machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3232: [Installation&On-site support] Leak test machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3233: [Installation&On-site support] Guage Check machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3234: [Installation&On-siiite support] Insulator Assy machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3235: [Installation&On-site support] Final Inspection machineNewNattapong Sukcharoen12 Jan 202616 Jan 2026

Actions
Project progress work #3236: [Installation&On-site support] Software master PLC System InstallationNewSermsak Prowee12 Jan 202616 Jan 2026

Actions
Project progress work #3237: [Installation&On-site support] Software InstallationNew12 Jan 202616 Jan 2026

Actions
Project progress work #3238: [Installation&On-site support] DB Set up and modificationNewSuphawat Tinaso12 Jan 202616 Jan 2026

Actions
Project progress work #3239: [Installation&On-site support] Windows application installationNewSuphawat Tinaso12 Jan 202616 Jan 2026

Actions
Project progress work #3240: [Installation&On-site support] Web application installationNewPhattarapong Kammee12 Jan 202616 Jan 2026

Actions
Project progress work #3241: [Installation&On-site support] Data validationNew12 Jan 202616 Jan 2026

Actions
Project progress work #3242: [Installation&On-site support] PLC Validation checkNewSermsak Prowee12 Jan 202616 Jan 2026

Actions
Project progress work #3243: [Installation&On-site support] Windows application validation checkNewSuphawat Tinaso12 Jan 202616 Jan 2026

Actions
Project progress work #3244: [Installation&On-site support] Web application validation checkNewPhattarapong Kammee12 Jan 202616 Jan 2026

Actions
Project progress work #3245: [Installation&On-site support] Teaching for UT/User Testing & Trial/Supports user feedbackNewSermsak Prowee12 Jan 202616 Jan 2026

Actions
Actions