Project

General

Profile

Actions

Project progress work #2809

open

Parent project #2807: [PJ250079] Traceability system for WA640

[Internal Design]

Added by Siriwilai Chaiwattanaphon 5 months ago. Updated about 1 month ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
10 Nov 2025
Due date:
06 Feb 2026 (43 days late)
% Done:

90%

Estimated time:
(Total: 88.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 3 (1 open2 closed)

Project progress work #3205: [Internal Design] Specification design ClosedNattapol Poeam10 Nov 202516 Nov 2025

Actions
Project progress work #3206: [Internal Design] Backup software / Parameter / HMI MachineClosedNattapong Sukcharoen22 Nov 202522 Nov 2025

Actions
Project progress work #6529: [Internal design] Data update and confirm WA640/740 LineIn ProgressNattapong Sukcharoen02 Feb 202606 Feb 2026

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 2 months ago

  • Status changed from New to Closed
Actions #2

Updated by Waraporn Promsopa about 1 month ago

  • Status changed from Closed to In Progress
Actions #3

Updated by Waraporn Promsopa about 1 month ago

  • Status changed from In Progress to New
Actions

Also available in: Atom PDF