44

26

27

SHINDENGEN (THAILAND) CO., LTD. - Parent project #3015: [PJ250090] Operation monito... Parent project #3015: [PJ250090] Operation monitoring system for ShinDengen Customization fee

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: In Progress
Start date: 27 Oct 2025
Due date: 20 Feb 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1680: [Coding] Weighing Receiving Project progress work #1680: [Coding] Weighing Receiving

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 27 Oct 2025
Due date: 16 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal

28

29

THAI MATTO NS CO., LTD. - Project progress work #2798: [Coding] Blender Process Project progress work #2798: [Coding] Blender Process

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 29 Oct 2025
Due date: 09 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal

30

THAI MATTO NS CO., LTD. - Project progress work #2804: [Coding] Delivery Project progress work #2804: [Coding] Delivery

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 30 Oct 2025
Due date: 13 Feb 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2799: [Coding] Blender Preparatio... Project progress work #2799: [Coding] Blender Preparation Record

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 30 Oct 2025
Due date: 09 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal

31

THAI MATTO NS CO., LTD. - Project progress work #2800: [Coding] Blender Data Record Project progress work #2800: [Coding] Blender Data Record

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 31 Oct 2025
Due date: 08 Feb 2026
Assignee: Surat Duangchiaw
Priority: Normal

1

45

2

3

A.N.I. LOGISTICS, LTD. - Project progress work #3372: [Installation&On-site suppo... Project progress work #3372: [Installation&On-site support] Teaching for Go live

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 16 Nov 2025
Assignee:
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3366: [Installation&On-site suppo... Project progress work #3366: [Installation&On-site support] Supports user feedback

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 23 Nov 2025
Assignee:
Priority: Normal
SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3303: [Internal Design] Project progress work #3303: [Internal Design]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 03 Nov 2025
Due date: 30 Nov 2025
Assignee:
Priority: Normal
THAI INABA FOODS COMPANY LIMITED - Project progress work #2865: [Installation&On-site suppo... Project progress work #2865: [Installation&On-site support] Go live

Project: THAI INABA FOODS COMPANY LIMITED
Status: In Progress
Start date: 03 Nov 2025
Due date:
Assignee: Taweesak Prumvised
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2801: [Coding] Blender RM Return Project progress work #2801: [Coding] Blender RM Return

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 03 Nov 2025
Due date: 12 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #1067: [Installation&On-site support] Project progress work #1067: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 01 Mar 2026
Assignee:
Priority: Normal

4

THAI MATTO NS CO., LTD. - Project progress work #2795: [Coding] Extruding Process Project progress work #2795: [Coding] Extruding Process

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 04 Nov 2025
Due date: 09 Jan 2026
Assignee: Taweesak Prumvised
Priority: Normal

5

NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #1418: [Coding] Check duplicated o... Project progress work #1418: [Coding] Check duplicated on scan

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 05 Nov 2025
Due date: 05 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal
NKT NIPPON KONPO (THAILAND) CO., LTD - Project progress work #1413: [Coding] Issue found Project progress work #1413: [Coding] Issue found

Project: NKT NIPPON KONPO (THAILAND) CO., LTD
Status: New
Start date: 05 Nov 2025
Due date: 05 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal

6

THAI INABA FOODS COMPANY LIMITED - Project progress work #2867: [Coding] HT Pegasus add re-... Project progress work #2867: [Coding] HT Pegasus add re-check function

Project: THAI INABA FOODS COMPANY LIMITED
Status: New
Start date: 06 Nov 2025
Due date: 08 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1593: [Coding] Extruding/Data Rec... Project progress work #1593: [Coding] Extruding/Data Record

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 06 Nov 2025
Due date: 08 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal

7

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Parent project #2807: [PJ250079] Traceability sys... Parent project #2807: [PJ250079] Traceability system for WA640

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: In Progress
Start date: 07 Nov 2025
Due date: 05 Mar 2026
Assignee: Ryo Nozaki
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2803: [Coding] Packing Project progress work #2803: [Coding] Packing

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 07 Nov 2025
Due date: 17 Feb 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2802: [Coding] Extruding WIP Return Project progress work #2802: [Coding] Extruding WIP Return

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 07 Nov 2025
Due date: 12 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal

8

THAI INABA FOODS COMPANY LIMITED - Project progress work #2867: [Coding] HT Pegasus add re-... Project progress work #2867: [Coding] HT Pegasus add re-check function

Project: THAI INABA FOODS COMPANY LIMITED
Status: New
Start date: 06 Nov 2025
Due date: 08 Nov 2025
Assignee: Taweesak Prumvised
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2884: [Coding] Production Schedul... Project progress work #2884: [Coding] Production Schedule - Backend

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 08 Nov 2025
Due date: 16 Feb 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal
46

9

10

THAI MATTO NS CO., LTD. - Project progress work #2806: [Coding] NCR Project progress work #2806: [Coding] NCR

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 10 Nov 2025
Due date: 10 Nov 2025
Assignee: Lux Aubon
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3142: [Installation&Onsite support] Project progress work #3142: [Installation&Onsite support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Nov 2025
Due date: 27 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #2809: [Internal Design] Project progress work #2809: [Internal Design]

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 10 Nov 2025
Due date: 06 Feb 2026
Assignee:
Priority: Normal

11

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3208: [Coding] Mechanical Project progress work #3208: [Coding] Mechanical

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 11 Nov 2025
Due date: 08 Dec 2025
Assignee: Nattawat Hannok
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3207: [Coding] Electrical Project progress work #3207: [Coding] Electrical

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 11 Nov 2025
Due date: 12 Dec 2025
Assignee: Taweesak Suriyon
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1706: [Coding] Dashboard report –... Project progress work #1706: [Coding] Dashboard report – Production monitoring

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 11 Nov 2025
Due date: 18 Dec 2025
Assignee: Thiraporn Amornsirinukorh
Priority: Normal

12

THAI MATTO NS CO., LTD. - Project progress work #2797: [Coding] Pre-Blend Project progress work #2797: [Coding] Pre-Blend

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 12 Nov 2025
Due date: 16 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #2796: [Coding] OM-Mixer Project progress work #2796: [Coding] OM-Mixer

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 12 Nov 2025
Due date: 16 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1681: [Coding] Weighing Project progress work #1681: [Coding] Weighing

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 12 Nov 2025
Due date: 16 Jan 2026
Assignee: Surat Duangchiaw
Priority: Normal

13

14

15

47

16

A.N.I. LOGISTICS, LTD. - Project progress work #3372: [Installation&On-site suppo... Project progress work #3372: [Installation&On-site support] Teaching for Go live

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 16 Nov 2025
Assignee:
Priority: Normal

17

A.N.I. LOGISTICS, LTD. - Project progress work #3376: [Installation&On-site suppo... Project progress work #3376: [Installation&On-site support] Go live

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 17 Nov 2025
Due date: 17 Nov 2025
Assignee:
Priority: Normal
ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. - Project progress work #3003: [Internal Design] Project progress work #3003: [Internal Design]

Project: ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD.
Status: New
Start date: 17 Nov 2025
Due date: 16 Dec 2025
Assignee: Anek Sanohkham
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #1288: [Installation&On-site suppo... Project progress work #1288: [Installation&On-site support] Software installation

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 17 Nov 2025
Due date: 06 Mar 2026
Assignee:
Priority: Normal

18

19

THAI MATTO NS CO., LTD. - Project progress work #2997: [Coding] Production Plannin... Project progress work #2997: [Coding] Production Planning (Work Instruction Sheet)

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 19 Nov 2025
Due date: 16 Feb 2026
Assignee: Thiraporn Amornsirinukorh
Priority: Normal

20

21

THAI INABA FOODS COMPANY LIMITED - Project progress work #2878: [installation&On-site suppo... Project progress work #2878: [installation&On-site support] Support Onsite

Project: THAI INABA FOODS COMPANY LIMITED
Status: In Progress
Start date: 21 Nov 2025
Due date:
Assignee: Nattaporn Chaiya
Priority: Normal

22

ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. - Project progress work #3002: [Requirement definition] Project progress work #3002: [Requirement definition]

Project: ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD.
Status: New
Start date: 24 Oct 2025
Due date: 22 Nov 2025
Assignee: Anek Sanohkham
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #3286: [Coding] Injection Project progress work #3286: [Coding] Injection

Project: THAI MATTO NS CO., LTD.
Status: New
Start date: 22 Nov 2025
Due date: 08 Feb 2026
Assignee: Taweesak Prumvised
Priority: Normal
48

23

A.N.I. LOGISTICS, LTD. - Project progress work #3366: [Installation&On-site suppo... Project progress work #3366: [Installation&On-site support] Supports user feedback

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 23 Nov 2025
Assignee:
Priority: Normal
SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3305: [Installation&On-site suppo... Project progress work #3305: [Installation&On-site support]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 23 Nov 2025
Due date: 30 Jan 2026
Assignee:
Priority: Normal

24

NIPPN (THAILAND) CO., LTD. - Project progress work #3182: [Installation&IOn-site supp... Project progress work #3182: [Installation&IOn-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Surasak Atchanawat
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #3181: [Installation&On-site support] Project progress work #3181: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Supatnchai Hempolchom
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #3180: [Installation&On-site support] Project progress work #3180: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Nattikorn Srisadet
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2933: [Installation&On-site suppo... Project progress work #2933: [Installation&On-site support] SIT Utility system

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 28 Dec 2025
Assignee:
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #1629: [Installation&On-site support] Project progress work #1629: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee:
Priority: Normal

25

26

SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3304: [Coding] Project progress work #3304: [Coding]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 26 Nov 2025
Due date: 20 Feb 2026
Assignee:
Priority: Normal
MITSUI PRECISION THAI CO., LTD. - Project progress work #3153: [Coding] Project progress work #3153: [Coding]

Project: MITSUI PRECISION THAI CO., LTD.
Status: In Progress
Start date: 26 Nov 2025
Due date: 28 Mar 2026
Assignee: Soraya Norasing
Priority: Normal

27

28

THAI MATTO NS CO., LTD. - Project progress work #1596: [Coding] Software test Project progress work #1596: [Coding] Software test

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 01 Aug 2025
Due date: 28 Nov 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

29

49

30

SHINDENGEN (THAILAND) CO., LTD. - Project progress work #3303: [Internal Design] Project progress work #3303: [Internal Design]

Project: SHINDENGEN (THAILAND) CO., LTD.
Status: New
Start date: 03 Nov 2025
Due date: 30 Nov 2025
Assignee:
Priority: Normal

1

AH BRAKE (THAILAND) CO., LTD. - Project progress work #4439: [Installation&On-site support] Project progress work #4439: [Installation&On-site support]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Parent project #2996: [PJ250088] MOC IoT system f... Parent project #2996: [PJ250088] MOC IoT system for wiring work AHT

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2934: [Installation&On-site suppo... Project progress work #2934: [Installation&On-site support] UAT

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 01 Dec 2025
Due date: 18 Jan 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2901: [Coding] Software development Project progress work #2901: [Coding] Software development

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 08 Feb 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2899: [Internal Design] Software ... Project progress work #2899: [Internal Design] Software system design

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #2810: [Coding] Master PLC Project progress work #2810: [Coding] Master PLC

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 01 Dec 2025
Due date: 20 Feb 2026
Assignee: Sermsak Prowee
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #1035: [Coding] Project progress work #1035: [Coding]

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 08 Feb 2026
Assignee: Anek Sanohkham
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #1034: [Internal Design] Project progress work #1034: [Internal Design]

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee: Anek Sanohkham
Priority: Normal

2

A.N.I. LOGISTICS, LTD. - Project progress work #3054: [Coding] Handy UI Script Project progress work #3054: [Coding] Handy UI Script

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2025
Due date: 02 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

3

4

A.N.I. LOGISTICS, LTD. - Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #3135: [Coding] Reprint Case mark ... Project progress work #3135: [Coding] Reprint Case mark document

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 04 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

5

A.N.I. LOGISTICS, LTD. - Project progress work #3101: [Coding] Web Development Project progress work #3101: [Coding] Web Development

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 26 Jun 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3343: [Internal Design] Project progress work #3343: [Internal Design]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Project progress work #3342: [Requirement definition] Project progress work #3342: [Requirement definition]

Project: AH BRAKE (THAILAND) CO., LTD.
Status: New
Start date: 05 Dec 2025
Due date: 12 Dec 2025
Assignee:
Priority: Normal
AH BRAKE (THAILAND) CO., LTD. - Parent project #3341: [PJ250103] MOC packing syst... Parent project #3341: [PJ250103] MOC packing system for AHT modification fee Convert to picking list

Project: AH BRAKE (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Dec 2025
Due date: 23 Dec 2025
Assignee: Nattapol Poeam
Priority: Normal

6

issue beginning this day issue ending this day issue beginning and ending this day