Estimated time: 18934.00 Spent time: 7923.40

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
2974 Project progress work New Normal [Installation&On-site support] Import master program IM data / UAT IM Process 0.00 19 Nov 2025 11:33 Actions
2973 Project progress work New Normal [Installation&On-site support] Import master program IV data / UAT IV Process 16.00 0.00 19 Nov 2025 11:32 Actions
2972 Project progress work New Normal [Installation&On-site support] UAT Inner packing Process PC with Handy 40.00 0.00 19 Nov 2025 11:31 Actions
2971 Project progress work New Normal [Installation&On-site support] Import master Ocr-Qpoint check 16.00 0.00 19 Nov 2025 11:28 Actions
2970 Project progress work New Normal [Installation&On-site support] Handy Set IP and Install APK 41 devices 16.00 0.00 19 Nov 2025 11:27 Actions
2969 Project progress work New Normal [Installation&On-site support] Create Table Master 8.00 0.00 19 Nov 2025 11:26 Actions
2968 Project progress work New Normal [Installation&On-site support] Install WebSocket controller Trim 16.00 0.00 19 Nov 2025 11:25 Actions
2967 Project progress work New Normal [Installation&On-site support] Panel 304.00 0.00 08 Dec 2025 11:38 Actions
2966 Project progress work New Normal [Installation&On-site support] Trim 424.00 0.00 19 Nov 2025 11:44 Actions
2953 Project progress work New Normal [Installation&On-site support] Production monitoring system UAT Nattapong Sukcharoen 40.00 0.00 18 Nov 2025 17:00 Actions
2951 Project progress work New Normal [Installation&On-site support] Air flow monitoring Panupong Raksakit 8.00 0.00 18 Nov 2025 16:56 Actions
2950 Project progress work New Normal [Installation&On-site support] Utility data monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2949 Project progress work New Normal [Installation&On-site support] Utility monitoring Panupong Raksakit 16.00 0.00 18 Dec 2025 14:23 Actions
2948 Project progress work New Normal [Installation&On-site support] Calling system Nattapong Sukcharoen 8.00 0.00 18 Nov 2025 16:41 Actions
2947 Project progress work New Normal [Installation&On-site support] Alarm monitoring Nattapong Sukcharoen 16.00 0.00 18 Nov 2025 16:40 Actions
2934 Project progress work New Normal [Installation&On-site support] UAT 72.00 0.00 18 Dec 2025 14:23 Actions
2933 Project progress work New Normal [Installation&On-site support] SIT Utility system 40.00 0.00 18 Dec 2025 14:23 Actions
2932 Project progress work New Normal [Installation&On-site support] SIT Production system 88.00 0.00 18 Dec 2025 14:24 Actions
2920 Project progress work New Normal [Installation&On-site support] Fix Issue Nattaporn Chaiya 0.00 18 Nov 2025 15:13 Actions
2903 Parent project In Progress Normal [PJ250096] Label Ryo Nozaki 0.00 13 Dec 2025 08:38 Actions
2902 Parent project In Progress Normal [PJ250082] ConMas i-Reporter 50 users On-premises update from 10users Anek Sanohkham 0.00 14 Nov 2025 12:01 Actions
2901 Project progress work New Normal [Coding] Software development 0.00 13 Nov 2025 13:50 Actions
2900 Project progress work New Normal [Internal Design] Hardware system design 40.00 0.00 13 Nov 2025 13:46 Actions
2899 Project progress work New Normal [Internal Design] Software system design 0.00 13 Nov 2025 13:46 Actions
2884 Project progress work In Progress Normal [Coding] Production Schedule - Backend Thiraporn Amornsirinukorh 16.00 56.00 13 Dec 2025 11:02 Actions
(226-250/627) Per page: 25, 50, 100