Project

General

Profile

For internal project work assignment report without Nozaki

« December 2025 | February »

Apply Clear

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1

28

THAI ASAHI DENSO CO., LTD. - Project progress work #2933: [Installation&On-site suppo... Project progress work #2933: [Installation&On-site support] SIT Utility system

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 28 Dec 2025
Assignee:
Priority: Normal

29

30

31

1

2

3

2

4

5

NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #3394: [Requirement definition] Project progress work #3394: [Requirement definition]

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 05 Jan 2026
Due date: 18 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3258: [Coding] Internal Test Project progress work #3258: [Coding] Internal Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 05 Jan 2026
Due date: 07 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3190: [Coding] Web application Project progress work #3190: [Coding] Web application

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 05 Jan 2026
Due date: 11 Jan 2026
Assignee: Phattarapong Kammee
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3187: [Coding] Windows applicatio... Project progress work #3187: [Coding] Windows application & Database

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 05 Jan 2026
Due date: 25 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal
PROSPIRA THAILAND CO., LTD. - Project progress work #1173: [Coding] Project progress work #1173: [Coding]

Project: PROSPIRA THAILAND CO., LTD.
Status: New
Start date: 05 Jan 2026
Due date: 02 Jun 2026
Assignee: Priroj Neamjarn
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1165: [Internal Design] Project progress work #1165: [Internal Design]

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 05 Jan 2026
Due date: 21 Jan 2026
Assignee: Kittisak Isarapongporn
Priority: Normal

6

OKAYA (THAILAND) CO., LTD. (BANGNA BRANCH) - Project progress work #6789: [Installation&On-site support] Project progress work #6789: [Installation&On-site support]

Project: OKAYA (THAILAND) CO., LTD. (BANGNA BRANCH)
Status: New
Start date: 06 Jan 2026
Due date: 21 Feb 2026
Assignee:
Priority: Normal
OKAYA (THAILAND) CO., LTD. (BANGNA BRANCH) - Parent project #3001: [PJ250087] Product Distribu... Parent project #3001: [PJ250087] Product Distribution System - CPF

Project: OKAYA (THAILAND) CO., LTD. (BANGNA BRANCH)
Status: In Progress
Start date: 06 Jan 2026
Due date: 18 Jun 2026
Assignee: Anek Sanohkham
Priority: Normal

7

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3258: [Coding] Internal Test Project progress work #3258: [Coding] Internal Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 05 Jan 2026
Due date: 07 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

8

NIPPN (THAILAND) CO., LTD. - Project progress work #6576: [Coding] Project progress work #6576: [Coding]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 08 Jan 2026
Due date: 23 Jun 2026
Assignee: Nattikorn Srisadet
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3259: [Coding] Final Test Project progress work #3259: [Coding] Final Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Jan 2026
Due date: 09 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

9

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3259: [Coding] Final Test Project progress work #3259: [Coding] Final Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Jan 2026
Due date: 09 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3252: [Coding] Process Control sy... Project progress work #3252: [Coding] Process Control system

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 08 Dec 2025
Due date: 09 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

10

3

11

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3190: [Coding] Web application Project progress work #3190: [Coding] Web application

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 05 Jan 2026
Due date: 11 Jan 2026
Assignee: Phattarapong Kammee
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4350: [Internal Design] Project progress work #4350: [Internal Design]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 11 Jan 2026
Due date: 01 Apr 2026
Assignee: Nattapol Poeam
Priority: Normal

12

NIPPN (THAILAND) CO., LTD. - Project progress work #3182: [Installation&IOn-site supp... Project progress work #3182: [Installation&IOn-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Surasak Atchanawat
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #3181: [Installation&On-site support] Project progress work #3181: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Supatnchai Hempolchom
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #3180: [Installation&On-site support] Project progress work #3180: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee: Nattikorn Srisadet
Priority: Normal
NIPPN (THAILAND) CO., LTD. - Project progress work #1629: [Installation&On-site support] Project progress work #1629: [Installation&On-site support]

Project: NIPPN (THAILAND) CO., LTD.
Status: In Progress
Start date: 24 Nov 2025
Due date: 12 Jan 2026
Assignee:
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #6641: [Internal design] System De... Project progress work #6641: [Internal design] System Design

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 08 Mar 2026
Assignee: Nattapol Poeam
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #4430: [Coding] Update software an... Project progress work #4430: [Coding] Update software and DB for new model

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 25 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4370: [Coding] Hardware procurement Project progress work #4370: [Coding] Hardware procurement

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 01 Mar 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4369: [Coding] Keyence Equipment Project progress work #4369: [Coding] Keyence Equipment

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 10 Feb 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4368: [Coding] Modify Pallet Project progress work #4368: [Coding] Modify Pallet

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 08 Mar 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4363: [Internal Design] Software ... Project progress work #4363: [Internal Design] Software System Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4354: [Internal Design] Project progress work #4354: [Internal Design]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 01 Apr 2026
Assignee: Nattapol Poeam
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #3396: [Coding] Project progress work #3396: [Coding]

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 08 Mar 2026
Assignee: Nattapol Poeam
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3261: [Coding] Taping Plan (FIFO) Project progress work #3261: [Coding] Taping Plan (FIFO)

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Jan 2026
Due date: 15 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3260: [Coding] Taping Label system Project progress work #3260: [Coding] Taping Label system

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Jan 2026
Due date: 30 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3245: [Installation&On-site suppo... Project progress work #3245: [Installation&On-site support] Teaching for UT/User Testing & Trial/Supports user feedback

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee: Sermsak Prowee
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3241: [Installation&On-site suppo... Project progress work #3241: [Installation&On-site support] Data validation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3237: [Installation&On-site suppo... Project progress work #3237: [Installation&On-site support] Software Installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 30 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3236: [Installation&On-site suppo... Project progress work #3236: [Installation&On-site support] Software master PLC System Installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee: Sermsak Prowee
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3193: [Coding] Machine data prepare Project progress work #3193: [Coding] Machine data prepare

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 10 Feb 2026
Assignee: Nattapong Sukcharoen
Priority: Normal

13

14

15

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3261: [Coding] Taping Plan (FIFO) Project progress work #3261: [Coding] Taping Plan (FIFO)

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Jan 2026
Due date: 15 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

16

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3245: [Installation&On-site suppo... Project progress work #3245: [Installation&On-site support] Teaching for UT/User Testing & Trial/Supports user feedback

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee: Sermsak Prowee
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3241: [Installation&On-site suppo... Project progress work #3241: [Installation&On-site support] Data validation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3236: [Installation&On-site suppo... Project progress work #3236: [Installation&On-site support] Software master PLC System Installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 16 Jan 2026
Assignee: Sermsak Prowee
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4448: [Installation&On-site support] Project progress work #4448: [Installation&On-site support]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4447: [Coding] Project progress work #4447: [Coding]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4446: [Internal Design] Project progress work #4446: [Internal Design]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4445: [Requirement definition] Project progress work #4445: [Requirement definition]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4444: [Installation&On-site support] Project progress work #4444: [Installation&On-site support]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4443: [Coding] Project progress work #4443: [Coding]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4442: [Internal Design] Project progress work #4442: [Internal Design]

Project: THAI YOKOREI CO., LTD.
Status: New
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Project progress work #4441: [Requirement Definition] Project progress work #4441: [Requirement Definition]

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee:
Priority: Normal
THAI YOKOREI CO., LTD. - Parent project #4385: [PJ260002] Camera system mo... Parent project #4385: [PJ260002] Camera system modification for Thailand configuration BCR

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee: Nattapol Poeam
Priority: Normal
THAI YOKOREI CO., LTD. - Parent project #4384: [PJ260001] BCR system for T... Parent project #4384: [PJ260001] BCR system for Thai Yokorei

Project: THAI YOKOREI CO., LTD.
Status: In Progress
Start date: 16 Jan 2026
Due date:
Assignee: Nattapol Poeam
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3262: [Coding] Taping label record Project progress work #3262: [Coding] Taping label record

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 16 Jan 2026
Due date: 21 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

17

4

18

NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #3394: [Requirement definition] Project progress work #3394: [Requirement definition]

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 05 Jan 2026
Due date: 18 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI ASAHI DENSO CO., LTD. - Project progress work #2934: [Installation&On-site suppo... Project progress work #2934: [Installation&On-site support] UAT

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 01 Dec 2025
Due date: 18 Jan 2026
Assignee:
Priority: Normal
A.N.I. LOGISTICS, LTD. - Project progress work #6690: [Issue] Project progress work #6690: [Issue]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 18 Jan 2026
Due date: 01 Mar 2026
Assignee:
Priority: Normal

19

NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4366: [Coding] Software development Project progress work #4366: [Coding] Software development

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 19 Jan 2026
Due date: 22 Feb 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4365: [Internal Design] Hardware ... Project progress work #4365: [Internal Design] Hardware Drawing Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 19 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4364: [Internal Design] Hardware ... Project progress work #4364: [Internal Design] Hardware System Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 19 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal

20

21

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3262: [Coding] Taping label record Project progress work #3262: [Coding] Taping label record

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 16 Jan 2026
Due date: 21 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
HOWA PACKAGING (THAILAND) CO., LTD. - Project progress work #3172: [Installation&On-site support] Project progress work #3172: [Installation&On-site support]

Project: HOWA PACKAGING (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Jan 2025
Due date: 21 Jan 2026
Assignee:
Priority: Normal
HOWA PACKAGING (THAILAND) CO., LTD. - Parent project #3043: [PJ250094] SR Jig for HOWA ... Parent project #3043: [PJ250094] SR Jig for HOWA PACKAGING (THAILAND) CO., LTD.

Project: HOWA PACKAGING (THAILAND) CO., LTD.
Status: In Progress
Start date: 05 Jan 2025
Due date: 21 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
THAI MATTO NS CO., LTD. - Project progress work #1165: [Internal Design] Project progress work #1165: [Internal Design]

Project: THAI MATTO NS CO., LTD.
Status: In Progress
Start date: 05 Jan 2026
Due date: 21 Jan 2026
Assignee: Kittisak Isarapongporn
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4356: [Installation&On-site support] Project progress work #4356: [Installation&On-site support]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 21 Jan 2026
Due date: 12 Jun 2026
Assignee: Nattapol Poeam
Priority: Normal
UNIMICRON (THAILAND) CO., LTD. - Project progress work #4352: [Installation&On-site support] Project progress work #4352: [Installation&On-site support]

Project: UNIMICRON (THAILAND) CO., LTD.
Status: New
Start date: 21 Jan 2026
Due date: 12 Jun 2026
Assignee: Nattapol Poeam
Priority: Normal

22

23

THAI ASAHI DENSO CO., LTD. - Project progress work #2932: [Installation&On-site suppo... Project progress work #2932: [Installation&On-site support] SIT Production system

Project: THAI ASAHI DENSO CO., LTD.
Status: In Progress
Start date: 08 Dec 2025
Due date: 23 Jan 2026
Assignee:
Priority: Normal

24

SIAM NITERRA CO., LTD. - Project progress work #1051: [Installation&On-site support] Project progress work #1051: [Installation&On-site support]

Project: SIAM NITERRA CO., LTD.
Status: New
Start date: 24 Jan 2026
Due date: 26 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
5

25

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #4430: [Coding] Update software an... Project progress work #4430: [Coding] Update software and DB for new model

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 25 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4365: [Internal Design] Hardware ... Project progress work #4365: [Internal Design] Hardware Drawing Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 19 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4364: [Internal Design] Hardware ... Project progress work #4364: [Internal Design] Hardware System Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 19 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal
NIDEC TECHNO MOTOR (THAILAND) CO., LTD. - Project progress work #4363: [Internal Design] Software ... Project progress work #4363: [Internal Design] Software System Design

Project: NIDEC TECHNO MOTOR (THAILAND) CO., LTD.
Status: New
Start date: 12 Jan 2026
Due date: 25 Jan 2026
Assignee:
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3187: [Coding] Windows applicatio... Project progress work #3187: [Coding] Windows application & Database

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 05 Jan 2026
Due date: 25 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal

26

SIAM NITERRA CO., LTD. - Project progress work #1051: [Installation&On-site support] Project progress work #1051: [Installation&On-site support]

Project: SIAM NITERRA CO., LTD.
Status: New
Start date: 24 Jan 2026
Due date: 26 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
SIAM NITERRA CO., LTD. - Parent project #1047: [PJ250025] Pokayoke inspect... Parent project #1047: [PJ250025] Pokayoke inspection system for SIAM NITERRA Co., Ltd.

Project: SIAM NITERRA CO., LTD.
Status: In Progress
Start date: 01 Jun 2025
Due date: 26 Jan 2026
Assignee: Nattapol Poeam
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #4431: [Installation&On-site suppo... Project progress work #4431: [Installation&On-site support] Software and DB for new model installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 26 Jan 2026
Due date: 30 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3263: [Coding] Check Machine status Project progress work #3263: [Coding] Check Machine status

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 26 Jan 2026
Due date: 27 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

27

ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3263: [Coding] Check Machine status Project progress work #3263: [Coding] Check Machine status

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 26 Jan 2026
Due date: 27 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
SHINDENGEN INDIA - Project progress work #5410: [Internal Design] Project progress work #5410: [Internal Design]

Project: SHINDENGEN INDIA
Status: New
Start date: 27 Jan 2026
Due date:
Assignee:
Priority: Normal
SHINDENGEN INDIA - Parent project #5408: [PJ260013] Operation monito... Parent project #5408: [PJ260013] Operation monitoring system for ShinDengen Phase01

Project: SHINDENGEN INDIA
Status: In Progress
Start date: 27 Jan 2026
Due date: 28 May 2026
Assignee: Nattapol Poeam
Priority: Normal

28

NIPPN (THAILAND) CO., LTD. - Project progress work #6580: [Coding] return RM to supplier Project progress work #6580: [Coding] return RM to supplier

Project: NIPPN (THAILAND) CO., LTD.
Status: New
Start date: 28 Jan 2026
Due date: 29 Jan 2026
Assignee: Nattikorn Srisadet
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3264: [Coding] Internal Test Project progress work #3264: [Coding] Internal Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 28 Jan 2026
Due date: 29 Jan 2026
Assignee: Soraya Norasing
Priority: Normal

29

NIPPN (THAILAND) CO., LTD. - Project progress work #6580: [Coding] return RM to supplier Project progress work #6580: [Coding] return RM to supplier

Project: NIPPN (THAILAND) CO., LTD.
Status: New
Start date: 28 Jan 2026
Due date: 29 Jan 2026
Assignee: Nattikorn Srisadet
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3264: [Coding] Internal Test Project progress work #3264: [Coding] Internal Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 28 Jan 2026
Due date: 29 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #2899: [Internal Design] Software ... Project progress work #2899: [Internal Design] Software system design

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee:
Priority: Normal
AIKAI LOGISTICS (THAILAND) CO., LTD - Project progress work #1034: [Internal Design] Project progress work #1034: [Internal Design]

Project: AIKAI LOGISTICS (THAILAND) CO., LTD
Status: New
Start date: 01 Dec 2025
Due date: 29 Jan 2026
Assignee: Anek Sanohkham
Priority: Normal

30

FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #4431: [Installation&On-site suppo... Project progress work #4431: [Installation&On-site support] Software and DB for new model installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 26 Jan 2026
Due date: 30 Jan 2026
Assignee: Suphawat Tinaso
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3265: [Coding] Final Test Project progress work #3265: [Coding] Final Test

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 30 Jan 2026
Due date: 30 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
ASIAN STANLEY. INTERNATIONAL LIMITED. - Project progress work #3260: [Coding] Taping Label system Project progress work #3260: [Coding] Taping Label system

Project: ASIAN STANLEY. INTERNATIONAL LIMITED.
Status: New
Start date: 12 Jan 2026
Due date: 30 Jan 2026
Assignee: Soraya Norasing
Priority: Normal
FTS AUTOMOTIVE (THAILAND) CO.,LTD - Project progress work #3237: [Installation&On-site suppo... Project progress work #3237: [Installation&On-site support] Software Installation

Project: FTS AUTOMOTIVE (THAILAND) CO.,LTD
Status: New
Start date: 12 Jan 2026
Due date: 30 Jan 2026
Assignee:
Priority: Normal

31

issue beginning this day issue ending this day issue beginning and ending this day