Project

General

Profile

Actions

Parent project #1047

open

[PJ250025] Pokayoke inspection system for SIAM NITERRA Co., Ltd.

Added by Siriporn Nimitmuenwai 5 months ago. Updated about 2 months ago.

Status:
In Progress
Priority:
Normal
Start date:
01 Jun 2025
Due date:
01 Jun 2025 (about 7 months late)

Subtasks 4 (2 open2 closed)

Project progress work #1048: [Requirement definition]ClosedNattapol Poeam01 Jun 202501 Jun 2025

Actions
Project progress work #1049: [Internal Design]ClosedNattapol Poeam01 Jun 202501 Jun 2025

Actions
Project progress work #1050: [Coding]NewNattapol Poeam01 Jun 202501 Jun 2025

Actions
Project progress work #1051: [Installation&On-site support]NewNattapol Poeam01 Jun 202501 Jun 2025

Actions

No data to display

Actions

Also available in: Atom PDF