Project progress work #95
closed
Parent project #560: [PJ230033]Label printing system concept1
Support installation for power supply and LAN cable for 20 points
Added by Ryo Nozaki about 2 years ago.
Updated over 1 year ago.
Description
Support installation for power supply and LAN cable for 20 points
- Control and coordinate between wiring or LAN installers and site supervisors at the installation plant.
- Config IP address of label printer and install in chip room
- Config access point for 4 points
- Install and config server of label print system
Files
- Status changed from New to In Progress
- Start date changed from 19 Oct 2023 to 25 Oct 2023
[25/10/23]
-Survey the area where the printer, electrical cabinet, LAN cabinet, and wire rails are installed above the ceiling.
-Measure the distance and install supports for fixing the light rail above the ceiling.
[26/10/23]
-Install supports for fixing the light rail above the ceiling.
- % Done changed from 0 to 70
[03/11/2023]
- Install the light rail And the LAN cable above the ceiling is already complete.
- The lighting control cabinet and LAN cabinet have been installed.
- Dragging electrical wires and LAN cables, preparing to enter the power control cabinet and LAN cabinet on 06/11/2023.
- Drill holes in the ceiling to prepare for installing electrical plugs. LAN cable connection point and Access point installation point
[06/11/2023]
- Install the power plug LAN cable connection point and Access point installation point
- Make electrical wires and LAN cables and prepare them to go into the power control cabinet and LAN cabinet.
[08/11/2023]
- Setup server for label printer system
- Setting printer name and IP Address
- % Done changed from 70 to 80
[07/11/2023]
- Install the power plug LAN cable connection point and Access point installation point
- Make electrical wires and LAN cables and prepare them to go into the power control cabinet and LAN cabinet.
[08/11/2023]
- Setup server for label printer system
- Setting printer name and IP Address
- Status changed from In Progress to Closed
- % Done changed from 80 to 100
- Project changed from 30 to Asian Stanley. International Limited
- Parent task set to #560