04 May 2024

16:01 Parent project #568 (Closed): [PJ230006]Uninterruptible Power System
Ryo Nozaki
15:39 Parent project #560 (Closed): [PJ230033]Label printing system concept1
Ryo Nozaki
15:34 Parent project #552 (Closed): [PJ240005]Handy terminal Process control system create 3 screen and wiring
Ryo Nozaki
15:32 Parent project #550 (Closed): [PJ230038]Handy terminal Process control system Screen program change/additional
Ryo Nozaki
15:27 Parent project #546 (Closed): [PJ240016]Handy terminal Process control system addtional line
Ryo Nozaki

01 May 2024

17:03 Project progress work #459 (Closed): support user for process control system
Ryo Nozaki
17:03 Project progress work #450 (Closed): Development web display
Ryo Nozaki
17:03 Project progress work #414 (Closed): Develop new screen of dashboard
Ryo Nozaki
17:03 Project progress work #347 (Closed): Meeting about modify display on TV
Ryo Nozaki
17:03 Project progress work #342 (Closed): Found a problem, unable to issue a report.
Ryo Nozaki
16:36 Problem-Bug #73 (Closed): Found 500 return error
Ryo Nozaki
16:33 Project progress work #8 (Closed): Support installation for power supply and LAN cable for 50 points
Ryo Nozaki
16:33 Project progress work #95 (Closed): Support installation for power supply and LAN cable for 20 points
Ryo Nozaki
16:11 Project progress work #477 (Closed): [Coding]ASI - Process Control System Phase2 -C# Windows app
Process Control System Phase2
-meeting
-get requirement.
Ryo Nozaki
16:08 Project progress work #465 (In Progress): [Coding]ASI - Process Control System Phase2 -Java
Ryo Nozaki
16:06 Problem-Bug #37 (Closed): UPS have problem
Ryo Nozaki
16:06 Sales support #36 (Closed): UPS can not use in some position at LINE model H9J
Ryo Nozaki
 