Sales support #36

closed

Parent project #568: [PJ230006]Uninterruptible Power System

UPS can not use in some position at LINE model H9J

Added by Atchai Konthong about 2 years ago. Updated over 1 year ago.

Status:
Closed
Priority:
Normal
Start date:
07 Oct 2023
Due date:
31 Oct 2023
% Done:

90%

Estimated time:
80.00 h
Spent time:
Finish date:

Description

UPS model 100 VCA can't use because main power have Wiring delta type only in some position when checked with BCN team got information that 4 position have problem, Divided into 2 solution

1.Change type the transformer from Auto Transformer to Isolate Transformer 2 position
2.Re-Wiring 2 position

and now sent PO to BCN for buy isolate transformer and wait K.Somchai confirm date for install and fix


Files

_PO-20231000002 bcn.pdf (680 KB) _PO-20231000002 bcn.pdf Atchai Konthong, 07 Oct 2023 15:34
Actions #1

Updated by Atchai Konthong about 2 years ago

  • Tracker changed from Project progress work to Sales support
Actions #2

Updated by Atchai Konthong about 2 years ago

  • Status changed from New to In Progress
Actions #3

Updated by Atchai Konthong about 2 years ago

Maker was informed that it will be builds completed by the end of this month for 2 Unit transformer isolate

Actions #4

Updated by Atchai Konthong about 2 years ago

  • % Done changed from 50 to 70
Actions #5

Updated by Ryo Nozaki about 2 years ago

  • Assignee changed from Atchai Konthong to Arunwit Isarapongporn
Actions #6

Updated by Arunwit Isarapongporn about 2 years ago

[27/10/2023]
Maker BCN
- Sent 2 UPS machines that submitted a claim back to ASI.

Actions #7

Updated by Arunwit Isarapongporn about 2 years ago

[31/10/2023]
- Maker BCN UPS can install UPS model 100 VCA, the remaining number to be installed is 9 units in line H9J. on 08/11/2023
- Waiting for installation of UPS with Isolate Transformer 2 position

Actions #8

Updated by Arunwit Isarapongporn about 2 years ago

  • % Done changed from 70 to 90

[30/11/2023]
- Maker BCN UPS can install UPS model 100 VCA, the remaining number to be installed is 8 units in line H9J. on 30/11/2023
- Installation of UPS with Isolate Transformer 2 position. on 30/11/2023
- A total of 11 UPS units were installed, but only 10 units could be installed due to a problem. One UPS had a power supply shortout.

Actions #9

Updated by Ryo Nozaki over 1 year ago

  • Status changed from In Progress to Closed
Actions #10

Updated by Ryo Nozaki over 1 year ago

  • Project changed from 31 to Asian Stanley. International Limited
  • Parent task set to #568