Project progress work #739
closedParent project #712: EKD System phase4 for ANI Ayuthaya
[Development] CKD process system phase4
Added by Priroj Neamjarn about 1 year ago. Updated 9 months ago.
Description
[Coding]
1)Android handy
2)tablet modification Java
3)Backend web socket (php)
Files
| ht_ani_phase4.apk (8.54 MB) ht_ani_phase4.apk | Priroj Neamjarn, 25 Dec 2024 17:36 | ||
| tablet_ani_phase4.apk (28.1 MB) tablet_ani_phase4.apk | Priroj Neamjarn, 25 Dec 2024 17:36 | ||
| CKD process system phase4 specifications Documentation EN Blueprint for ANI_R4.pptx (10.3 MB) CKD process system phase4 specifications Documentation EN Blueprint for ANI_R4.pptx | Priroj Neamjarn, 25 Dec 2024 17:36 | ||
| Q-Gate process system specifications Documentation EN Blueprint for ANI_R1.pptx (5.94 MB) Q-Gate process system specifications Documentation EN Blueprint for ANI_R1.pptx | Priroj Neamjarn, 25 Dec 2024 17:36 | ||
| UnitTest_CKD_Process_system_phase4.xls (4.04 MB) UnitTest_CKD_Process_system_phase4.xls | Priroj Neamjarn, 25 Dec 2024 17:37 |
Updated by Priroj Neamjarn about 1 year ago
today
-Schedule plan
-Prepare an Android project
tomorrow
-Receive process
Updated by Priroj Neamjarn about 1 year ago
- Status changed from New to In Progress
today
-Receive process
tomorrow
-Receive process
Updated by Priroj Neamjarn about 1 year ago
today
-Receive process
tomorrow
-Receive process
Updated by Priroj Neamjarn about 1 year ago
today
-Receive process
tomorrow
-Receive process
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 0 to 10
today
-Receive process
tomorrow
-Receive process
Updated by Priroj Neamjarn about 1 year ago
today
-Receive process
tomorrow
-Inner Packing process
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing process
tomorrow
-Inner Packing process
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing process
tomorrow
-Inner Packing process
Updated by Priroj Neamjarn about 1 year ago
today
- Inner Packing process
tomorrow
-Inner Packing process
-Login process
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 10 to 20
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing process
-Travel to the office
tomorrow
-Inner Packing process
-Login process
Updated by Priroj Neamjarn about 1 year ago
- Start date changed from 02 Oct 2024 to 18 Oct 2024
today
-Inner Packing process
tomorrow
-Inner Packing process
-Login process
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing process
-Login process
tomorrow
-Login process
-Outer Packing Process
Updated by Priroj Neamjarn about 1 year ago
today
-Login process
tomorrow
-Outer Packing Process
-Inner Packing Process (new customer request)
Updated by Priroj Neamjarn about 1 year ago
today
-New Main menu (phase 4)
-Outer Packing Process
-Inner Packing Process (new customer request)
Updated by Priroj Neamjarn about 1 year ago
today
-New Main menu (phase 4)
-Inner Packing Process (new customer request)
-Multi scan handy
tomorrow
-Outer Packing Process
-Multi scan handy
-Lock screen
Updated by Priroj Neamjarn about 1 year ago
today
-Inner Packing Process (new customer request)
-Multi scan handy
tomorrow
-Outer Packing Process
-Multi scan handy
-Lock screen
Updated by Priroj Neamjarn about 1 year ago
today
-Outer Packing Process
-Multi scan handy
-Lock screen
tomorrow
-Outer Packing Process
-Multi scan handy
-Lock screen
Updated by Priroj Neamjarn about 1 year ago
today
-Outer Packing Process
-Multi scan handy
tomorrow
-Outer Packing Process
-Lock screen
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 20 to 30
today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
Updated by Priroj Neamjarn about 1 year ago
today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
-Receive Finish Case
Updated by Priroj Neamjarn about 1 year ago
today
-Outer Packing Process
tomorrow
-Lock screen
-Receive Finish Case
Updated by Priroj Neamjarn about 1 year ago
today
-Receive Finish Case
tomorrow
-Lock screen
-Receive Finish Case
Updated by Priroj Neamjarn about 1 year ago
today
-Receive Finish Case
-Lock screen
tomorrow
-Receive Finish Case
Updated by Priroj Neamjarn about 1 year ago
today
-Receive Finish Case
tomorrow
-Receive Finish Case
Updated by Priroj Neamjarn about 1 year ago
today
-Receive Finish Case (Handy)
tomorrow
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 30 to 40
today
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
tomorrow
-Move Finish Case (Handy)
Updated by Priroj Neamjarn about 1 year ago
today
-Move Finish Case (Handy)
-Setup Finish Case (Handy)
tomorrow
-Setup Finish Case (Handy)
-Setup Finish Case (Tablet)
Updated by Priroj Neamjarn about 1 year ago
today
-Setup Finish Case (Handy)
tomorrow
-Setup Finish Case (Handy)
-Setup Finish Case (Tablet)
Updated by Priroj Neamjarn about 1 year ago
today
-Setup Finish Case (Handy)
tomorrow
-Setup Finish Case (Handy)
-Setup Finish Case (Tablet)
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 40 to 50
today
-Setup Finish Case (Handy)
tomorrow
-Setup Finish Case (Tablet)
-Vanning Finish Case (Handy)
-Vanning Finish Case (Tablet)
Updated by Priroj Neamjarn about 1 year ago
today
-Setup Finish Case (Handy)
-Setup Finish Case (Tablet)
tomorrow
-Vanning Finish Case (Handy)
-Vanning Finish Case (Tablet)
Updated by Priroj Neamjarn about 1 year ago
today
-Vanning Finish Case (Handy)
-Vanning Finish Case (Tablet)
tomorrow
-Edit Tag Receive label
-PC Schedule Receive, Schedule Staging
Updated by Priroj Neamjarn about 1 year ago
today
-Vanning Finish Case (Tablet)
-Edit Tag Receive label
tomorrow
-PC Schedule Receive, Schedule Staging
Updated by Priroj Neamjarn about 1 year ago
today
-Edit Tag Receive label
-PC Schedule Receive, Schedule Staging
tomorrow
-PC Schedule Receive, Schedule Staging
Updated by Priroj Neamjarn about 1 year ago
today
-PC Schedule Receive, Schedule Staging, Schedule Inner
tomorrow
-PC Schedule Outer, Schedule Vanning
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 50 to 60
today
-PC Schedule Receive, Schedule Staging, Schedule Inner
PC Schedule Outer, Schedule Vanning
tomorrow
-PC Schedule Outer, Schedule Vanning
Updated by Priroj Neamjarn about 1 year ago
today
PC Schedule Outer, Schedule Vanning
Q-Point detail report
tomorrow
Packing daily summary report
Packing monthly summary report
Updated by Priroj Neamjarn about 1 year ago
today
Q-Point detail report
tomorrow
Packing daily summary report
Packing monthly summary report
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 60 to 70
today
Packing daily summary report
tomorrow
Packing daily summary report
Packing monthly summary report
Updated by Priroj Neamjarn about 1 year ago
today
Packing daily summary report
tomorrow
Packing daily summary report
Packing monthly summary report
Updated by Priroj Neamjarn about 1 year ago
today
Packing daily summary report
Meeting with ANI
tomorrow
Packing monthly summary report
Updated by Priroj Neamjarn about 1 year ago
- % Done changed from 70 to 80
today
-Packing monthly summary report
-Dashboard
tomorrow
-Dashboard
Updated by Priroj Neamjarn about 1 year ago
today
-Adjust the power meter calculation function of OTIC.
-Meeting to discuss the specifications of the Stock management system (MAST.)
tomorrow
-Adjust the power meter calculation function of OTIC.
Updated by Priroj Neamjarn about 1 year ago
today
-Adjust the power meter calculation function of OTIC.
tomorrow
-Adjust the power meter calculation function of OTIC.
Updated by Priroj Neamjarn about 1 year ago
today
-Internal test case
tomorrow
-Dashboard
-Q-Gate (new requirement)
Updated by Priroj Neamjarn about 1 year ago
today
-create screen Q-Gate for Handy
-create screen Q-Gate for Tablet
-create Socket API
tomorrow
-create screen Q-Gate for Handy
-create screen Q-Gate for Tablet
-create Socket API
Updated by Priroj Neamjarn about 1 year ago
today
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
tomorrow
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
Updated by Priroj Neamjarn about 1 year ago
today
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
tomorrow
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
Updated by Priroj Neamjarn about 1 year ago
today
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
tomorrow
-Coding Q-Gate for Handy
-Coding screen Q-Gate for Tablet
-Coding Socket API
Updated by Priroj Neamjarn about 1 year ago
today
-Coding screen Q-Gate for Tablet
-Coding Socket API
tomorrow
-Coding screen Q-Gate for Tablet
-Coding Socket API
-Coding Web
Updated by Priroj Neamjarn about 1 year ago
today
-Coding screen Q-Gate for Tablet
-Coding Socket API
tomorrow
-Coding Web
Updated by Priroj Neamjarn about 1 year ago
today
-Coding Web Pegasus System
tomorrow
-Coding Web Pegasus System
Updated by Priroj Neamjarn about 1 year ago
today
-Coding Web Pegasus System
tomorrow
-Internal test
Updated by Priroj Neamjarn 12 months ago
- File ht_ani_phase4.apk ht_ani_phase4.apk added
- File tablet_ani_phase4.apk tablet_ani_phase4.apk added
- File CKD process system phase4 specifications Documentation EN Blueprint for ANI_R4.pptx CKD process system phase4 specifications Documentation EN Blueprint for ANI_R4.pptx added
- File Q-Gate process system specifications Documentation EN Blueprint for ANI_R1.pptx Q-Gate process system specifications Documentation EN Blueprint for ANI_R1.pptx added
- File UnitTest_CKD_Process_system_phase4.xls UnitTest_CKD_Process_system_phase4.xls added
- Status changed from In Progress to Confirmation request
-internal test
Updated by Kittisak Isarapongporn 12 months ago
- Parent task changed from #713 to #712
Updated by Kittisak Isarapongporn 12 months ago
- Subject changed from CKD process system phase4 to [Development] CKD process system phase4
Updated by Priroj Neamjarn 12 months ago
today
Test and prepare for system installation.
Updated by Priroj Neamjarn 12 months ago
today
Fix bug Tablet, Handy, Web for system installation.
Updated by Priroj Neamjarn 11 months ago
today
-Prepare to install the application.
Updated by Priroj Neamjarn 11 months ago
today
-Prepare to install the application.
Updated by Kittisak Isarapongporn 11 months ago
- Status changed from Confirmation request to Close request
Updated by Priroj Neamjarn 11 months ago
today
-Update Setup/Vanning Process
-Update QGate Process
Updated by Ryo Nozaki 10 months ago
- Status changed from Close request to Closed
Updated by Priroj Neamjarn 9 months ago
today
-Fix Bug Vanning and Add function keep log approve sc flag
tomorrow
-Fix bug q-gate