Project

General

Profile

Actions

Project progress work #4349

open

Parent project #3346: [PJ2500104] IoT system for Unimicron(Thailand)Co., Ltd Phase01

[Requirement definition]

Added by Siriwilai Chaiwattanaphon 2 months ago. Updated about 1 month ago.

Status:
In Progress
Priority:
Normal
Start date:
15 Dec 2025
Due date:
03 May 2026 (Due in 43 days)
% Done:

80%

Estimated time:
(Total: 728.00 h)
Finish date:
Programming skills:
No development
DB skills:
Not using
OS skills:
Not using

Subtasks 5 (1 open4 closed)

Project progress work #6618: [Requirement definition] Received POClosedNattapol Poeam15 Dec 202518 Dec 2025

Actions
Project progress work #6619: [Requirement definition] Internal meetingClosedNattapol Poeam12 Jan 202625 Jan 2026

Actions
Project progress work #6620: [Requirement definition] Kick-off meetingClosedNattapol Poeam09 Feb 202615 Feb 2026

Actions
Project progress work #6621: [Requirement definition] Requirements confirmationClosedNattapol Poeam12 Jan 202608 Mar 2026

Actions
Project progress work #6623: [Requirement definition] Software developmentNewNattapol Poeam02 Mar 202603 May 2026

Actions
Actions #1

Updated by Siriwilai Chaiwattanaphon 2 months ago

  • Tracker changed from Parent project to Project progress work
  • % Done set to 0
  • Programming skills No development added
  • DB skills Not using added
  • OS skills Not using added
Actions

Also available in: Atom PDF