Project

General

Profile

Actions

Parent project #1516

closed

[PJ250059] FTS AUTOMOTIVE (THAILAND) CO.,LTD.

Added by Siriwilai Chaiwattanaphon 6 months ago. Updated 26 days ago.

Status:
Closed
Priority:
Normal
Start date:
09 Jan 2026
Due date:
13 Jan 2026

Subtasks 6 (0 open6 closed)

Project progress work #2844: [Requirement definition]ClosedNattapol Poeam

Actions
Project progress work #2845: [Internal Design]ClosedNattapol Poeam

Actions
Project progress work #2846: [Coding]ClosedNattapol Poeam09 Jan 202613 Jan 2026

Actions
Project progress work #6673: [Coding] Genal fix of Assy Line3 and Assy Line4ClosedSermsak Prowee12 Jan 202613 Jan 2026

Actions
Project progress work #6721: [Coding] Fix Gauge Check's status of Assy Line4 that stamp NGClosedSermsak Prowee09 Jan 202609 Jan 2026

Actions
Project progress work #2847: [Installation&On-site support]ClosedNattapol Poeam

Actions
Actions

Also available in: Atom PDF