Activity
From 09 Feb 2026 to 18 Feb 2026
18 Feb 2026
- 13:45 Project progress work #6674 (Closed): [Coding] Internal Test
- 13:45 Project progress work #6674 (Closed): [Coding] Internal Test
- 13:43 Parent project #1516 (Closed): [PJ250059] FTS AUTOMOTIVE (THAILAND) CO.,LTD.
- 13:41 Parent project #1516 (In Progress): [PJ250059] FTS AUTOMOTIVE (THAILAND) CO.,LTD.
- 13:43 Project progress work #2846 (Closed): [Coding]
- 13:41 Project progress work #2846 (In Progress): [Coding]
- 13:43 Project progress work #6673 (Closed): [Coding] Genal fix of Assy Line3 and Assy Line4
- 13:42 Project progress work #6673 (Closed): [Coding] Genal fix of Assy Line3 and Assy Line4
12 Feb 2026
11 Feb 2026
- 11:10 Project progress work #6567 (Closed): [Coding] Create a program outline
- 11:10 Project progress work #6567 (Closed): [Coding] Create a program outline
- 11:07 Project progress work #6566 (Closed): [Coding] Create a program outline
- 11:07 Project progress work #6566 (Closed): [Coding] Create a program outline
- 09:54 Project progress work #6544 (Closed): [Installation&On-site support] Design & Installation Line Welding 740
- 09:54 Project progress work #6544 (Closed): [Installation&On-site support] Design & Installation Line Welding 740
- 09:51 Project progress work #6543 (In Progress): [Installation&On-site support] Design & Installation Line WA640
- 09:51 Project progress work #6543 (In Progress): [Installation&On-site support] Design & Installation Line WA640
- 08:35 Project progress work #2809 (New): [Internal Design]
- 08:32 Project progress work #2809 (In Progress): [Internal Design]
- 08:34 Project progress work #6529 (In Progress): [Internal design] Data update and confirm WA640/740 Line
- 08:34 Project progress work #6529 (In Progress): [Internal design] Data update and confirm WA640/740 Line
- 08:31 Project progress work #2808 (Closed): [Requirement definition]
- 08:31 Project progress work #2808 (In Progress): [Requirement definition]
10 Feb 2026
- 16:43 Project progress work #6527 (Closed): [Installation&On-site support] Installation Ethernet Module and back up program WA640 Line
- 16:41 Project progress work #6527 (Closed): [Installation&On-site support] Installation Ethernet Module and back up program WA640 Line
- 16:43 Project progress work #6526 (Closed): [Installation&On-site support] Control cabinet and Lan wiring
- 16:39 Project progress work #6526 (Closed): [Installation&On-site support] Control cabinet and Lan wiring
- 16:42 Project progress work #6528 (In Progress): [Installation&On-site support] Installation Ethernet Module and back up program WA640/740 Line
- 16:42 Project progress work #6528 (In Progress): [Installation&On-site support] Installation Ethernet Module and back up program WA640/740 Line