Project

General

Profile

For internal project work assignment report without Nozaki

Zoom in Zoom out « February | April »

months from Apply Clear

Status

In Progress
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal

Assignee

Total estimated time

680.00
32.00
16.00
72.00
560.00

Total spent time

0.00
0.00
0.00
0.00
0.00

Updated

06 May 2026 15:01
02 Apr 2026 09:51
02 Apr 2026 09:39
29 Apr 2026 14:26
06 May 2026 15:01
 
 
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Tomas Tech All Project Management
 
 
TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
 
 
 
 
In Progress
Parent project #6731: [PJ260035] Traceability system for TOYO ADVANCED

Project: TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
Status: In Progress
Start date: 17 Feb 2026
Due date: 05 May 2026
Assignee: Nattapol Poeam
Priority: Normal
 
 
 
 
New 100%
Project progress work #6740: [Installation&On-site support]

Project: TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
Status: New
Start date: 17 Feb 2026
Due date: 31 Mar 2026
Assignee:
Priority: Normal
 
 
 
 
 
New 100%
Project progress work #6737: [Requirement definition]

Project: TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
Status: New
Start date: 19 Mar 2026
Due date: 27 Mar 2026
Assignee:
Priority: Normal
 
 
 
 
 
New 100%
Project progress work #6738: [Internal Design]

Project: TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
Status: New
Start date: 23 Mar 2026
Due date: 23 Apr 2026
Assignee:
Priority: Normal
 
 
 
 
 
New 100%
Project progress work #6739: [Coding]

Project: TOYO ADVANCED TECHNOLOGIES AUTOMOBILE COMPONENTS (THAILAND) CO., LTD.
Status: New
Start date: 23 Apr 2026
Due date: 05 May 2026
Assignee:
Priority: Normal
 

Also available in: PDF PNG