Hours: 55963.60

Date User Activity Issue Comment Hours
04 Nov 2023 Kittisak Isarapongporn Development Project progress work #91: Modify Pegasus. Checking the script and test result from packing app (found the wrong reader number) 3.00 Actions
04 Nov 2023 Kittisak Isarapongporn Meeting Project progress work #199: Internal test Initial the testing 5.00 Actions
04 Nov 2023 Ryo Nozaki Make document Sales support #62: CKD project phase3 Proposal activities + requirements definition 2.00 Actions
04 Nov 2023 Ryo Nozaki Make document Sales support #62: CKD project phase3 Proposal activities + requirements definition 9.00 Actions
04 Nov 2023 Suchin Viyasing Development Project progress work #196: Test Program 8.00 Actions
04 Nov 2023 Kamol Anekchatnuntakool Development Project progress work #105: [Coding]Data linkage function 6.00 Actions
04 Nov 2023 Nattapol Poeam Make document Project progress work #186: Create demo unit for keyence Program and HMI 8.00 Actions
04 Nov 2023 Nattapol Poeam Make document Project progress work #186: Create demo unit for keyence All documents related to this work 8.00 Actions
04 Nov 2023 Nattapol Poeam Make document Project progress work #187: Create demo unit for WD 10sets Estimate cost Demo-Kit New 8.00 Actions
04 Nov 2023 Arunwit Isarapongporn Development Sales support #48: Redmine email notifications Redmine email notifications setting 8.00 Actions
04 Nov 2023 Nattapol Poeam Make document Project progress work #87: IoT Equipment for machine operation project Update document layout plant 8.00 Actions
04 Nov 2023 Nattapol Poeam Make document Sales support #175: EV charger installation project Update document about installation EV-Charger 8.00 Actions
04 Nov 2023 Kamol Anekchatnuntakool Development Problem-Bug #184: Found an incorrect configure about the packing app reader number 2.00 Actions
04 Nov 2023 Suchin Viyasing Development Project progress work #193: Test Program 8.00 Actions
04 Nov 2023 Nattapol Poeam Make document Project progress work #119: [Internal Design] DB and various functions, man-hour calculation Update document about reequipment from customer after meeting 03/11/23 4.00 Actions
04 Nov 2023 Arunwit Isarapongporn Make document Project progress work #95: Support installation for power supply and LAN cable for 20 points 1.00 Actions
04 Nov 2023 Arunwit Isarapongporn Installation Project progress work #95: Support installation for power supply and LAN cable for 20 points 1.00 Actions
04 Nov 2023 Arunwit Isarapongporn Meeting Project progress work #159: ConMas i-Reporter teaching for NTPT staff 1.00 Actions
04 Nov 2023 Arunwit Isarapongporn Development Sales support #48: Redmine email notifications 1.00 Actions
04 Nov 2023 Arunwit Isarapongporn Installation Project progress work #95: Support installation for power supply and LAN cable for 20 points 8.00 Actions
04 Nov 2023 Arunwit Isarapongporn Installation Sales support #36: UPS can not use in some position at LINE model H9J 1.00 Actions
03 Nov 2023 Santi Srichankaew Development Sales support #31: [FY2023]Common management for Santi PC deverlop 8.00 Actions
03 Nov 2023 Soraya Norasing Installation Sales support #178: Support to start using the system for Label printing system Support to start using the system for Label printing system 8.00 Actions
03 Nov 2023 Suchin Viyasing Development Project progress work #195: Test Program Leaning function PLC Mistubishi 8.00 Actions
03 Nov 2023 Nattapol Poeam Meeting Project progress work #119: [Internal Design] DB and various functions, man-hour calculation Meeting about requiment from production section input data in production line and UI for monitoring Main UI 4.00 Actions
(7101-7125/7308) Per page: 25, 50, 100