Parent project #901: [PJ250014] Production management system for NIPPN (Thailand) Co.,Ltd.
Project progress work #1629: [Installation&On-site support]
Project progress work #3180: [Installation&On-site support]
Project progress work #3181: [Installation&On-site support]
Project progress work #3182: [Installation&IOn-site support]
Parent project #1290: [PJ250053] WIFI Wiring for NIPPN (Thailand) Co.,Ltd.
Parent project #3399: [PJ250110] WIFI Wiring modification work for NIPPN (Thailand) Co.,Ltd.
Project progress work #4357: [Requirement definition]
Project progress work #4358: [Internal Design]
Project progress work #4360: [Installation&On-site support]
Project progress work #4466: [Installation&On-site support] Wiring LAN Cable and config access point

Status

In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
In Progress
New
New
New
New
New

Priority

Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal
Normal

Total estimated time

3134.00
200.00
8.00
8.00
8.00

Total spent time

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Updated

11 Dec 2025 10:10
08 Jan 2026 16:49
08 Jan 2026 16:49
08 Jan 2026 16:50
08 Jan 2026 16:49
11 Dec 2025 10:04
17 Jan 2026 13:40
06 Jan 2026 14:22
06 Jan 2026 14:22
06 Jan 2026 14:23
17 Jan 2026 13:40
17 Jan 2026 13:40
 
 
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Tomas Tech All Project Management
NIPPN (THAILAND) CO., LTD.
In Progress
In Progress 0%
In Progress 0%
In Progress 0%
In Progress 0%
In Progress
New 50%
New 50%
 

Also available in: PDF PNG