Estimated time: 1304.00 Spent time: 0.00

# Tracker Status Priority Subject Assignee Total estimated time Total spent time Updated
3168 Project progress work New Normal [Coding] Label Template Soraya Norasing 40.00 0.00 09 Dec 2025 16:24 Actions
3167 Project progress work New Normal [Coding] Printer Setting Soraya Norasing 8.00 0.00 09 Dec 2025 16:23 Actions
3166 Project progress work New Normal [Coding] Stock management Soraya Norasing 16.00 0.00 09 Dec 2025 16:23 Actions
3165 Project progress work New Normal [Coding] Outbound Manual Soraya Norasing 0.00 09 Dec 2025 16:22 Actions
3164 Project progress work New Normal [Coding] Outbound Crusher Soraya Norasing 24.00 0.00 09 Dec 2025 16:21 Actions
3163 Project progress work New Normal [Coding] Delivery Outbound Soraya Norasing 24.00 0.00 09 Dec 2025 16:20 Actions
3162 Project progress work New Normal [Coding] Work Outbound Soraya Norasing 32.00 0.00 09 Dec 2025 16:20 Actions
3161 Project progress work New Normal [Coding] QC Check Manual Soraya Norasing 16.00 0.00 09 Dec 2025 16:19 Actions
3160 Project progress work New Normal [Coding] QC Schedule Soraya Norasing 32.00 0.00 09 Dec 2025 16:18 Actions
3159 Project progress work New Normal [Coding] QC Check Soraya Norasing 40.00 0.00 09 Dec 2025 16:17 Actions
3158 Project progress work New Normal [Coding] Confirm Receive Soraya Norasing 16.00 0.00 09 Dec 2025 16:15 Actions
3157 Project progress work New Normal [Coding] Inbound Manual Soraya Norasing 16.00 0.00 09 Dec 2025 16:13 Actions
3156 Project progress work New Normal [Coding] Inbound Schedule (Rank A B) Soraya Norasing 24.00 0.00 09 Dec 2025 16:12 Actions
3155 Project progress work New Normal [Coding] Inbound Schedule (No rank) Soraya Norasing 40.00 0.00 09 Dec 2025 16:11 Actions
3153 Project progress work New Normal [Coding] Soraya Norasing 336.00 0.00 09 Dec 2025 16:24 Actions
2832 Project progress work New Normal [Coding] Stock Management -WH Ronnagon Kongsuwan 16.00 0.00 04 Nov 2025 13:55 Actions
2831 Project progress work New Normal [Coding] Outbound Delivery Page -WH Ronnagon Kongsuwan 24.00 0.00 04 Nov 2025 13:54 Actions
2830 Project progress work New Normal [Coding] Print Finished Goods Pay In Stock Sheet -PD Ronnagon Kongsuwan 16.00 0.00 04 Nov 2025 13:53 Actions
2829 Project progress work New Normal [Coding] Outbound FG (Production) To WH Page -WH,PD Ronnagon Kongsuwan 40.00 0.00 04 Nov 2025 13:52 Actions
2828 Project progress work New Normal [Coding] IQC FG Page -PD Ronnagon Kongsuwan 16.00 0.00 04 Nov 2025 13:50 Actions
2827 Project progress work New Normal [Coding] Outbound Material Usage Page -PD Ronnagon Kongsuwan 24.00 0.00 04 Nov 2025 13:50 Actions
2826 Project progress work New Normal [Coding] Inbound Production Page -PD Ronnagon Kongsuwan 40.00 0.00 04 Nov 2025 13:49 Actions
2825 Project progress work New Normal [Coding] Import Schedule FG Production (Plan) -PD Ronnagon Kongsuwan 8.00 0.00 04 Nov 2025 13:47 Actions
2824 Project progress work New Normal [Coding] Print Raw Material Request -WH,PD Ronnagon Kongsuwan 16.00 0.00 04 Nov 2025 13:46 Actions
2823 Project progress work New Normal [Coding] Raw Material Request Page -WH,PD Ronnagon Kongsuwan 16.00 0.00 04 Nov 2025 13:45 Actions