04 Nov 2023 Nattapol Poeam Make document Project progress work #119: [Internal Design] DB and various functions, man-hour calculation Update document about reequipment from customer after meeting 03/11/23 4.00 Actions
03 Nov 2023 Nattapol Poeam Meeting Project progress work #119: [Internal Design] DB and various functions, man-hour calculation Meeting about requiment from production section input data in production line and UI for monitoring Main UI 4.00 Actions
03 Nov 2023 Nattapol Poeam Design Project progress work #119: [Internal Design] DB and various functions, man-hour calculation Design function calculation time Bekido and other function 4.00 Actions
03 Nov 2023 Ryo Nozaki Meeting Project progress work #143: Production IoT project requirements and support project 4.00 Actions
26 Oct 2023 Ryo Nozaki Make document Project progress work #143: Production IoT project requirements and support project 2.00 Actions
25 Oct 2023 Ryo Nozaki Make document Project progress work #143: Production IoT project requirements and support project 1.00 Actions
24 Oct 2023 Ryo Nozaki Meeting Project progress work #143: Production IoT project requirements and support project 10.00 Actions
20 Oct 2023 Ryo Nozaki Meeting Sales support #57: Production IoT project requirements definition Meeting with Kishio san and exprain about wiring problem 2.00 Actions