Date User Activity Issue Comment Hours
18 May 2024 Konlawat Saechee Installation Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project Install CT and Install Powermerter 8.00 Actions
18 May 2024 Teeradon Yuensakul Installation Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , CT Installation and wiring 9.30 Actions
17 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
17 May 2024 Teeradon Yuensakul Installation Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , Prepare Device for Installation in at (18/05/2024 to 19/05/2024) 8.00 Actions
16 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
16 May 2024 Teeradon Yuensakul Meeting Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , Monthly Meeting about work at shutdown factory (Installation ) 8.00 Actions
15 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
15 May 2024 Konlawat Saechee Meeting Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project JATH Safety training 4.00 Actions
14 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
14 May 2024 Nattapol Poeam Meeting Parent project #553: [PJ240004]Infrastructure IoT system for Jtekt Automotive Internal test function program with K.Panupong 4.00 Actions
13 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
12 May 2024 Teeradon Yuensakul Installation Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , Power meter Installation and some wiring 9.30 Actions
11 May 2024 Teeradon Yuensakul Installation Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , Power Meter Installation 8.00 Actions
10 May 2024 Teeradon Yuensakul Installation Project progress work #599: (Power Meter and CT ) Wiring and Installation Loop2 ,4 and Loop6 , prepare document for installation at (11/05/2024) 8.00 Actions
07 May 2024 Teeradon Yuensakul Development Project progress work #588: Flow Meter and Power Meter MODBUS protocol setting Modbus setting 8.00 Actions
06 May 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Test Program and Dashboard Development 8.00 Actions
06 May 2024 Nattapol Poeam Installation Project progress work #405: [Requirement definition] Infrastructure IoT system for Jtekt Automotive Support installation 8.00 Actions
06 May 2024 Teeradon Yuensakul Development Project progress work #588: Flow Meter and Power Meter MODBUS protocol setting Modbus setting 8.00 Actions
06 May 2024 Teeradon Yuensakul Development Parent project #553: [PJ240004]Infrastructure IoT system for Jtekt Automotive Flow Meter Modbus setting 8.00 Actions
03 May 2024 Teeradon Yuensakul Development Parent project #553: [PJ240004]Infrastructure IoT system for Jtekt Automotive Power Meter Modbus Setting 8.00 Actions
02 May 2024 Teeradon Yuensakul Installation Parent project #553: [PJ240004]Infrastructure IoT system for Jtekt Automotive Program Installation 8.00 Actions
01 May 2024 Santi Srichankaew Installation Project progress work #412: [Installation&On-site support] Hardware installation for Infrastructure IoT Project 400.00 Actions
24 Apr 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
23 Apr 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
22 Apr 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions