Hours: 5552.40

Date User Activity Issue Comment Hours
08 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
05 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
05 Jul 2024 Nattapol Poeam Development Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring Revised program section weigth CT 8.00 Actions
04 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
04 Jul 2024 Phatthadon Inthachot Design Project progress work #635: support Bekido Project Survey signal OK NG 8.00 Actions
04 Jul 2024 Nattapol Poeam Meeting Project progress work #655: [ Weekly work update meeting ] Minutes of Meeting IoT infrastructure system Meeting about update progress work 8.00 Actions
03 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
03 Jul 2024 Nattapol Poeam Development Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring Revised program section bekido,OEE formula 8.00 Actions
02 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
02 Jul 2024 Nattapol Poeam Installation Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring Update program 8.00 Actions
01 Jul 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
30 Jun 2024 Konlawat Saechee Installation Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project Iot project 8.00 Actions
29 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
28 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
27 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
27 Jun 2024 Nattapol Poeam Meeting Project progress work #655: [ Weekly work update meeting ] Minutes of Meeting IoT infrastructure system Meeting IoT infrastructure system 8.00 Actions
27 Jun 2024 Konlawat Saechee Meeting Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project meeting update progress and check Wiring Power meter (Loop2) 8.00 Actions
26 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
26 Jun 2024 Konlawat Saechee Installation Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project Setting Parameter and check Wiring Power meter (Loop1 3 4 5) 8.00 Actions
25 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
25 Jun 2024 Konlawat Saechee Installation Project progress work #611: [Installation&On-site support] Hardware installation for Infrastructure IoT Project Setting Parameter and check Wiring Power meter (Loop1) 8.00 Actions
24 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
21 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
20 Jun 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
20 Jun 2024 Nattapol Poeam Meeting Project progress work #141: [Task]Deverlop HMI Bekido and OA monitoring Meeting on-site about problem of IoT Project and Infrastructure project 8.00 Actions
(251-275/658) Per page: 25, 50, 100