Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 88.00

Date User Activity Issue Comment Hours
09 Jan 2024 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
15 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
14 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
13 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
12 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
09 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
08 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
07 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
06 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
05 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
04 Dec 2023 Woraphong Wernsantiah Development Project progress work #355: Deverlop OEE % data analysis OEE% Cal Function 8.00 Actions
    (1-11/11)