Hours: 11.00

Date User Activity Issue Comment Hours
13 Dec 2023 Ryo Nozaki Meeting Sales support #231: Replace procejet from D100 to KV8000 and XD02 Contenue proposal and customer said set budjet at April 2024 1.00 Actions
06 Dec 2023 Ryo Nozaki Make document Sales support #231: Replace procejet from D100 to KV8000 and XD02 Create quote 2.00 Actions
01 Dec 2023 Ryo Nozaki Meeting Sales support #231: Replace procejet from D100 to KV8000 and XD02 4.00 Actions
16 Nov 2023 Ryo Nozaki Meeting Sales support #231: Replace procejet from D100 to KV8000 and XD02 4.00 Actions
    (1-4/4)