Project progress work #2982: [Installation&On-site suppo... Project progress work #2982: [Installation&On-site support] Install Hardware weight scale (9 Set)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 22 Nov 2025
Due date: 30 Nov 2025
Assignee:
Priority: Normal

1

Project progress work #2983: [Installation&On-site suppo... Project progress work #2983: [Installation&On-site support] UAT of weight scale (9 Set)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 01 Dec 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal

2

Project progress work #3091: [Coding] Manual Inbound Project progress work #3091: [Coding] Manual Inbound

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 02 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
Project progress work #3054: [Coding] Handy UI Script Project progress work #3054: [Coding] Handy UI Script

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2025
Due date: 02 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

3

Project progress work #3092: [Coding] Manual Outbound Project progress work #3092: [Coding] Manual Outbound

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Dec 2025
Due date: 03 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
Project progress work #3072: [Coding] WS api and fronten... Project progress work #3072: [Coding] WS api and frontend script fixing

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 01 Oct 2025
Due date: 03 Dec 2025
Assignee:
Priority: Normal

4

Project progress work #3138: [Coding] Trouble Report Project progress work #3138: [Coding] Trouble Report

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 02 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
Project progress work #3135: [Coding] Reprint Case mark ... Project progress work #3135: [Coding] Reprint Case mark document

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 04 Dec 2025
Due date: 04 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal

5

Project progress work #3101: [Coding] Web Development Project progress work #3101: [Coding] Web Development

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 26 Jun 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2991: [Installation&On-site suppo... Project progress work #2991: [Installation&On-site support] UAT of weight scale (1 Set)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 23 Nov 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2988: [Installation&On-site suppo... Project progress work #2988: [Installation&On-site support] Training User

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 13 Nov 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2983: [Installation&On-site suppo... Project progress work #2983: [Installation&On-site support] UAT of weight scale (9 Set)

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 01 Dec 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2976: [Installation&On-site suppo... Project progress work #2976: [Installation&On-site support] Training User

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 13 Nov 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2967: [Installation&On-site suppo... Project progress work #2967: [Installation&On-site support] Panel

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #2966: [Installation&On-site suppo... Project progress work #2966: [Installation&On-site support] Trim

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 05 Dec 2025
Assignee:
Priority: Normal
Project progress work #1067: [Installation&On-site support] Project progress work #1067: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 03 Nov 2025
Due date: 05 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
Parent project #1058: [PJ250037] CKD system Phase 06 Parent project #1058: [PJ250037] CKD system Phase 06

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Aug 2025
Due date: 05 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

6

50

7

8

9

10

11

12

13

51

14

15

Project progress work #3148: [Installation&On-site support] Project progress work #3148: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Sep 2025
Due date: 15 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal
Project progress work #3142: [Installation&Onsite support] Project progress work #3142: [Installation&Onsite support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Nov 2025
Due date: 15 Dec 2025
Assignee: Yutthapong Sricha
Priority: Normal
Project progress work #3141: [Installation&On-site suppo... Project progress work #3141: [Installation&On-site support]

Project: A.N.I. LOGISTICS, LTD.
Status: New
Start date: 10 Nov 2025
Due date: 15 Dec 2025
Assignee: Tanong Amnuaypornsri
Priority: Normal
Parent project #1022: [PJ250028] IKD Management S... Parent project #1022: [PJ250028] IKD Management System for A.N.I.

Project: A.N.I. LOGISTICS, LTD.
Status: In Progress
Start date: 01 Oct 2024
Due date: 15 Dec 2025
Assignee: Kittisak Isarapongporn
Priority: Normal

16

17

18

19

20

52

21

22

23

24

25

26

27

1

28

29

30

31

1

2

3

issue beginning this day issue ending this day issue beginning and ending this day