Parent project #901

open

[PJ250014] Production management system for NIPPN (Thailand) Co.,Ltd.

Added by Kittisak Isarapongporn 9 months ago. Updated 8 days ago.

Status:
In Progress
Priority:
Normal
Start date:
06 Mar 2025
Due date:
12 Jan 2026 (Due in 24 days)
Spent time:
(Total: 1444.00 h)

Files


Subtasks 72 (5 open67 closed)

Project progress work #902: [Documentation] Get requirements of projectClosedKittisak Isarapongporn14 Mar 202512 Jun 2025

Actions
Project progress work #1126: [Coding] Master data Closed18 Aug 202513 Nov 2025

Actions
Project progress work #1553: [Coding] Supplier name informationClosedNattikorn Srisadet11 Sep 202512 Sep 2025

Actions
Project progress work #1556: [Coding] Customer masterClosedNattikorn Srisadet15 Sep 202516 Sep 2025

Actions
Project progress work #1557: [Coding] Item masterClosedNattikorn Srisadet02 Sep 202502 Sep 2025

Actions
Project progress work #1558: [Coding] Supplier mapClosedNattikorn Srisadet03 Sep 202513 Nov 2025

Actions
Project progress work #1559: [Coding] Standard Packing MasterClosedNattikorn Srisadet21 Aug 202521 Aug 2025

Actions
Project progress work #1560: [Coding] Location masterClosedNattikorn Srisadet22 Aug 202522 Aug 2025

Actions
Project progress work #1562: [Coding] User masterClosedNattikorn Srisadet25 Aug 202525 Aug 2025

Actions
Project progress work #1563: [Coding] User Credential masterClosedNattikorn Srisadet26 Aug 202526 Aug 2025

Actions
Project progress work #1565: [Coding] Authority MasterClosedNattikorn Srisadet27 Aug 202527 Aug 2025

Actions
Project progress work #1567: [Coding] Bill of MaterialsClosedNattikorn Srisadet09 Sep 202511 Sep 2025

Actions
Project progress work #1569: [Coding] NFT ProductClosedNattikorn Srisadet18 Aug 202519 Aug 2025

Actions
Project progress work #1570: [Coding] Pending ReasonClosedNattikorn Srisadet20 Aug 202520 Aug 2025

Actions
Project progress work #1684: [Coding] TippingPlaceClosedSupatnchai Hempolchom27 Oct 202503 Nov 2025

Actions
Project progress work #1690: [Coding] Timing of tippingClosedSupatnchai Hempolchom27 Oct 202503 Nov 2025

Actions
Project progress work #1691: [Coding] BlendingClosedSupatnchai Hempolchom28 Oct 202531 Oct 2025

Actions
Project progress work #1692: [Coding] Warehouse masterClosedSupatnchai Hempolchom28 Oct 202531 Oct 2025

Actions
Project progress work #1693: [Coding] Email notificationsClosedSupatnchai Hempolchom10 Oct 202514 Oct 2025

Actions
Project progress work #2879: [Coding] BOM apply all functionsClosedNattikorn Srisadet05 Nov 202508 Nov 2025

Actions
Project progress work #2880: [Coding] Blending instruction BOM&MasterClosedNattikorn Srisadet10 Nov 202512 Nov 2025

Actions
Project progress work #1325: [Coding] Stock ManagementClosedNattikorn Srisadet29 Aug 202503 Nov 2025

Actions
Project progress work #1538: [Coding] Stock inquiy/reportClosedNattikorn Srisadet04 Sep 202504 Sep 2025

Actions
Project progress work #1539: [Coding] Stock MaintenanceClosedNattikorn Srisadet01 Sep 202501 Sep 2025

Actions
Project progress work #1541: [Coding] StocktakingClosedNattikorn Srisadet29 Aug 202529 Aug 2025

Actions
Project progress work #1544: [Coding] Puchase InstructionsClosedNattikorn Srisadet17 Sep 202523 Sep 2025

Actions
Project progress work #1545: [Coding] PO MaterialClosedNattikorn Srisadet24 Sep 202530 Sep 2025

Actions
Project progress work #1685: [Coding] MRP - PO Material RequestClosedNattikorn Srisadet01 Oct 202503 Nov 2025

Actions
Project progress work #1506: [Coding] Schedule/Non-ScheduleClosed08 Sep 202511 Nov 2025

Actions
Project progress work #1507: [Coding] PO CustomerClosedSupatnchai Hempolchom08 Sep 202516 Sep 2025

Actions
Project progress work #1508: [Coding] PO planningClosedSupatnchai Hempolchom15 Sep 202522 Sep 2025

Actions
Project progress work #1509: [Coding] Outbound scheduleClosedSupatnchai Hempolchom23 Sep 202529 Sep 2025

Actions
Project progress work #1510: [Coding] OutboundClosedSupatnchai Hempolchom26 Sep 202527 Sep 2025

Actions
Project progress work #1512: [Coding] Picking/FG/Delivery Schedule GenerateClosedSupatnchai Hempolchom01 Oct 202502 Oct 2025

Actions
Project progress work #1513: [Coding] RM Requistion sheet &scheduleClosedSupatnchai Hempolchom03 Oct 202506 Oct 2025

Actions
Project progress work #1514: [Coding] Issues Blending formula sheetClosedSupatnchai Hempolchom07 Oct 202509 Oct 2025

Actions
Project progress work #1527: [Coding] Inbound schedule RMClosedNattikorn Srisadet20 Oct 202520 Oct 2025

Actions
Project progress work #1528: [Coding] Inbound HistoryClosedNattikorn Srisadet20 Oct 202521 Oct 2025

Actions
Project progress work #1532: [Coding] Incoming PlanClosedNattikorn Srisadet06 Oct 202507 Oct 2025

Actions
Project progress work #1533: [Coding] Add RMClosedSupatnchai Hempolchom03 Nov 202503 Nov 2025

Actions
Project progress work #1534: [Coding] FG - Print label FGClosedNattikorn Srisadet10 Oct 202518 Oct 2025

Actions
Project progress work #1536: [Coding] QC FG Release ProductClosedNattikorn Srisadet22 Oct 202523 Oct 2025

Actions
Project progress work #1686: [Coding] Delivery PlanningClosedSupatnchai Hempolchom14 Oct 202514 Oct 2025

Actions
Project progress work #1688: [Coding] Monthly Inventory reportClosedSupatnchai Hempolchom27 Oct 202530 Oct 2025

Actions
Project progress work #1689: [Coding] Dashboard UIClosedSupatnchai Hempolchom17 Oct 202518 Oct 2025

Actions
Project progress work #1708: [Coding] Inbound schedule ProductionClosedNattikorn Srisadet24 Oct 202524 Oct 2025

Actions
Project progress work #1709: [Coding] Inbound schedule FGClosedNattikorn Srisadet21 Oct 202531 Oct 2025

Actions
Project progress work #2688: [Coding] Packaging & Labeling Condition Inspection RecordClosedNattikorn Srisadet22 Oct 202530 Oct 2025

Actions
Project progress work #2689: [Coding] Dashboard BackendClosedSupatnchai Hempolchom17 Oct 202529 Oct 2025

Actions
Project progress work #2881: [Coding] Installation of NFT functions to AWSClosedSupatnchai Hempolchom07 Nov 202511 Nov 2025

Actions
Project progress work #2882: [Coding] FG - Print label FGClosedNattikorn Srisadet10 Oct 202518 Oct 2025

Actions
Project progress work #2883: [Coding] Packaging & Labeling Condition Inspection RecordClosedNattikorn Srisadet22 Oct 202530 Oct 2025

Actions
Project progress work #1609: [Coding] WarehouseClosed08 Oct 202502 Nov 2025

Actions
Project progress work #1610: [Coding] Incoming PlanClosedSurasak Atchanawat08 Oct 202510 Oct 2025

Actions
Project progress work #1608: [Coding] Login , Menu and othersClosedSurasak Atchanawat08 Oct 202508 Oct 2025

Actions
Project progress work #1611: [Coding] Picking Plan - Full bagClosedSurasak Atchanawat14 Oct 202515 Oct 2025

Actions
Project progress work #1612: [Coding] Picking Plan - WeighingClosedSurasak Atchanawat16 Oct 202517 Oct 2025

Actions
Project progress work #1613: [Coding] Weighing ReceivingClosedSurasak Atchanawat18 Oct 202518 Oct 2025

Actions
Project progress work #1614: [Coding] Weighing OutClosedSurasak Atchanawat20 Oct 202521 Oct 2025

Actions
Project progress work #1694: [Coding] Production[3F]ClosedSurasak Atchanawat22 Oct 202528 Oct 2025

Actions
Project progress work #1695: [Coding] Production[2F]ClosedSurasak Atchanawat28 Oct 202531 Oct 2025

Actions
Project progress work #1696: [Coding] DeliveryClosedSurasak Atchanawat31 Oct 202502 Nov 2025

Actions
Project progress work #1697: [Coding] Stock ManagementClosedSurasak Atchanawat10 Oct 202510 Oct 2025

Actions
Project progress work #1625: [Coding] Internal final testClosedKittisak Isarapongporn01 Oct 202517 Nov 2025

Actions
Project progress work #1626: [Internal Design] System DesignClosed20 Mar 202512 Jun 2025

Actions
Project progress work #1627: [Requirement definition] ClosedKittisak Isarapongporn06 Mar 202513 Jun 2025

Actions
Project progress work #1628: [Internal Design] Hardware procurementClosed20 May 202512 Aug 2025

Actions
Project progress work #1629: [Installation&On-site support]New24 Nov 202512 Jan 2026

Actions
Project progress work #3180: [Installation&On-site support]NewNattikorn Srisadet24 Nov 202512 Jan 2026

Actions
Project progress work #3181: [Installation&On-site support]NewSupatnchai Hempolchom24 Nov 202512 Jan 2026

Actions
Project progress work #3182: [Installation&IOn-site support]NewSurasak Atchanawat24 Nov 202512 Jan 2026

Actions
Project progress work #2697: [Coding] System integrate TestNewSurasak Atchanawat22 Oct 202517 Nov 2025

Actions
Actions #1

Updated by Kittisak Isarapongporn 9 months ago

  • Project changed from Tomas Tech Co.,Ltd. to NIPPN (Thailand) Co.,Ltd.
Actions #2

Updated by Karnthida Wannasiwaporn 8 months ago

  • Subject changed from [PJ250010] Production Management System to [PJ250014] Production Management System
Actions #3

Updated by Siriporn Nimitmuenwai 4 months ago

  • Subject changed from [PJ250014] Production Management System to [PJ250014] Production management system for NIPPN (Thailand) Co.,Ltd.
  • Assignee set to Kittisak Isarapongporn