Actions
Project progress work #1611
closedParent project #901: [PJ250014] Production management system for NIPPN (Thailand) Co.,Ltd.
Project progress work #1609: [Coding] Warehouse
[Coding] Picking Plan - Full bag
Start date:
14 Oct 2025
Due date:
15 Oct 2025
% Done:
100%
Estimated time:
16.00 h
Finish date:
15 Oct 2025
Programming skills:
Windows/C#
DB skills:
Not using
OS skills:
Not using
Updated by Siriwilai Chaiwattanaphon 2 months ago
- Due date changed from 26 Sep 2025 to 15 Oct 2025
- Status changed from New to In Progress
- Start date changed from 25 Sep 2025 to 14 Oct 2025
- % Done changed from 0 to 60
Updated by Siriwilai Chaiwattanaphon 2 months ago
- Status changed from In Progress to Close request
- Finish date set to 15 Oct 2025
Updated by Siriwilai Chaiwattanaphon about 2 months ago
- Status changed from Close request to Closed