Project progress work #852

closed

Parent project #776: [PJ240052] Infrastructure IoT system for NTN Manufacturing (Thailand) Hardware Soi6 PT Soi3

[ Installation & On-site support] Software installation PLC

Added by Nattapol Poeam about 1 year ago. Updated about 1 month ago.

Status:
Closed
Priority:
Normal
Start date:
20 Jan 2025
Due date:
08 Feb 2025
% Done:

100%

Estimated time:
120.00 h (Total: 300.00 h)
Finish date:
Programming skills:
PLC/Keyence
DB skills:
Not using
OS skills:
Not using

Description

Program installation and testing
1. Soi 3
2. Soi 6
3. Pinthong


Subtasks 3 (0 open3 closed)

Project progress work #856: [ Installation & On-site support] Program PLC Installation Soi3ClosedKonlawat Saechee20 Jan 202525 Jan 2025

Actions
Project progress work #857: [ Installation & On-site support] Program PLC Installation Soi6ClosedKonlawat Saechee27 Jan 202501 Feb 2025

Actions
Project progress work #858: [ Installation & On-site support] Program PLC Installation PintongClosedKonlawat Saechee03 Feb 202508 Feb 2025

Actions
Actions #1

Updated by Nattapol Poeam about 1 year ago

  • Subject changed from Program installation PLC to [ Installation & On-site support] Software installation PLC
Actions #2

Updated by Siriwilai Chaiwattanaphon about 1 month ago

  • Status changed from New to Closed
Actions