Parent project #2812

closed

[PJ250089] Traceability system for Welding 740

Added by Siriwilai Chaiwattanaphon 8 months ago. Updated 24 days ago.

Status:
Closed
Priority:
Normal
Assignee:
Start date:
20 Dec 2025
Due date:
12 May 2026

Subtasks 19 (0 open19 closed)

Project progress work #2813: [Requirement definition]Closed

Actions
Project progress work #2814: [Internal Design]Closed

Actions
Project progress work #2815: [Coding]Closed02 Feb 202608 May 2026

Actions
Project progress work #6567: [Coding] Create a program outlineClosedSermsak Prowee02 Feb 202606 Feb 2026

Actions
Project progress work #6674: [Coding] Internal TestClosedSermsak Prowee12 Feb 202613 Feb 2026

Actions
Project progress work #6783: [Coding] Program Machine 740 LineClosedNattapong Sukcharoen16 Feb 202620 Feb 2026

Actions
Project progress work #7180: [Coding] Update software and DB for new modelClosedSuphawat Tinaso23 Mar 202627 Mar 2026

Actions
Project progress work #7182: [Coding] Program Machine 640 LineClosedNattapong Sukcharoen03 Mar 202610 Mar 2026

Actions
Project progress work #7362: [Coding] CSV file and FTP Client Programming.ClosedSermsak Prowee30 Apr 202601 May 2026

Actions
Project progress work #8264: [Coding] Fix issue of CSV file and FTP Client Programming.ClosedSermsak Prowee07 May 202608 May 2026

Actions
Project progress work #2816: [Installation&On-site support]Closed20 Dec 202512 May 2026

Actions
Project progress work #4433: [Installation&On-site support] Software and DB for new model installationClosedSuphawat Tinaso23 Mar 202627 Mar 2026

Actions
Project progress work #6544: [Installation&On-site support] Design & Installation Line Welding 740ClosedTaweesak Suriyon20 Dec 202508 Jan 2026

Actions
Project progress work #6784: [Installation&On-site support] Installation Program Machine 740 LineClosedNattapong Sukcharoen23 Feb 202627 Feb 2026

Actions
Project progress work #6785: [Installation&On-site support] Install Database and program view dataClosedPattanasak Chaonchom04 Mar 202605 Mar 2026

Actions
Project progress work #6862: [Installation&On-site support] Program Machine confirm testClosedNattapong Sukcharoen04 Mar 202605 Mar 2026

Actions
Project progress work #7181: [Installation&On-site support] Migrate to production server.ClosedSuphawat Tinaso09 Apr 202610 Apr 2026

Actions
Project progress work #7202: [Installation&On-site support] Onsite install and testing programClosedSermsak Prowee23 Feb 202624 Mar 2026

Actions
Project progress work #8265: [Installation&On-site support] Onsite fix issue of CSV file and FTP Client Programming.ClosedSermsak Prowee12 May 202612 May 2026

Actions
Actions