Project progress work #225

closed

Parent project #530: [PJ230054] CKD process management system phase3 for ANI

CCTV Installation

Added by Nattapol Poeam about 2 years ago. Updated about 2 months ago.

Status:
Closed
Priority:
Normal
Start date:
14 Nov 2023
Due date:
01 Jan 2024
% Done:

100%

Estimated time:
100.00 h
Spent time:
Finish date:
Programming skills:
DB skills:
OS skills:

Description

CCTV Installation


Files

Actions #1

Updated by Nattapol Poeam about 2 years ago

[ To day ]
- Contact supplier CCTV shadjan To bring CCTV equipment to test on 30/11/23 at 1:00 PM at A.N.I.
Equipment list
1. DS-7608NXI-K2/8 port
2. DS-2CD1023G0E-I 4 mm.
3. DS-2CD1023G0E-I 2.8 mm.
[ Next action ]
- Pick up the device to learn how to configure the device on 27/11/23 at 10:00 at Office shadjan. ( K.Aunchalee )
- Take the equipment for testing at A.N.I on 30/11/23 at 1 p.m.

Actions #2

Updated by Nattapol Poeam about 2 years ago

  • % Done changed from 10 to 50

[ To day ]
Pick up the device to learn how to configure the device
[ Next action ]
Take the equipment for testing at A.N.I on 30/11/23 at 1 p.m.

Actions #3

Updated by Nattapol Poeam about 2 years ago

  • % Done changed from 50 to 60

[ To day ]
- Site survey installation point CCTV line 10,11,12
- Wire way point
- position installation PC,Display,Label print, keyboard
- position installation in control room
[ Next Action ]
- Send dimension PC,Display to Custumer
- Start wiring work on 17/12/23

Actions #4

Updated by Ryo Nozaki over 1 year ago

  • Status changed from In Progress to Closed
Actions #5

Updated by Ryo Nozaki over 1 year ago

  • Project changed from 89 to A.N.I. LOGISTICS, LTD.
  • Parent task set to #530
Actions #6

Updated by Siriwilai Chaiwattanaphon about 2 months ago

  • % Done changed from 60 to 100
Actions