[PJ250052] Infrastructure IoT system for NTN Manufacturing(Thailand) NTPT

Added by Siriporn Nimitmuenwai 5 months ago. Updated 13 days ago.

Status:
In Progress
Priority:
Normal
Start date:
25 Aug 2025
Due date:
19 Jan 2026 (16 days late)
Spent time:
(Total: 64.00 h)

Files


Subtasks 14 (6 open8 closed)

Project progress work #1298: [Requirement definition]NewNattapol Poeam25 Aug 202514 Sep 2025

Actions
Project progress work #1299: [Internal Design] Electrical drawing designClosedPhatthadon Inthachot01 Sep 202514 Sep 2025

Actions
Project progress work #1300: [Coding]In ProgressSuphawat Tinaso15 Sep 202505 Oct 2025

Actions
Project progress work #1302: [Coding]NewNattaporn Chaiya15 Sep 202505 Oct 2025

Actions
Project progress work #1303: [Coding]NewKonlawat Saechee15 Sep 202505 Oct 2025

Actions
Project progress work #1304: [Installation&On-site support]New16 Dec 202519 Jan 2026

Actions
Project progress work #4407: [Installation&On-site support] Clone project to ruk-com serverClosedWorawit Khantamool16 Dec 202516 Dec 2025

Actions
Project progress work #4408: [Installation&On-site support] Web development Air FlowClosedWorawit Khantamool12 Jan 202613 Jan 2026

Actions
Project progress work #4409: [Installation&On-site support] Improved performance of Query getDataSummary15Min to be fasterClosedWorawit Khantamool15 Jan 202615 Jan 2026

Actions
Project progress work #4410: [Installation&On-site support] Web development Air FlowClosedWorawit Khantamool19 Jan 202619 Jan 2026

Actions
Problem-Bug #4419: [Issue]New12 Jan 202619 Jan 2026

Actions
Problem-Bug #4420: [Issue] Validate data power meterClosedSuphawat Tinaso15 Jan 202619 Jan 2026

Actions
Problem-Bug #4421: [Issue] Manual insert recovery data power meterClosedSuphawat Tinaso12 Jan 202617 Jan 2026

Actions
Problem-Bug #4422: [Issue] Modify Airflow data to insert 1 minute/timeClosedSuphawat Tinaso15 Jan 202615 Jan 2026

Actions
Actions