Hours: 7.00

Project Date User Activity Issue Comment Hours
SIAM NITORI Co., Ltd. 17 Jul 2025 Yuki Osawa Meeting Project progress work #1016: Asprova Phase 2 Implementation Had a meeting with Kamimura-san 3.00 Actions
SIAM NITORI Co., Ltd. 16 Jul 2025 Yuki Osawa Meeting Project progress work #1016: Asprova Phase 2 Implementation Had a meeting with Nakao-san 1.00 Actions
SIAM NITORI Co., Ltd. 14 Jul 2025 Yuki Osawa Meeting Project progress work #1016: Asprova Phase 2 Implementation Had a meeting with Kamimura-san 3.00 Actions
    (1-3/3)