OTICS (Thailand) Co., Ltd. 19 Dec 2025 Priroj Neamjarn Make document Project progress work #679: Power meter monitoring Make handover document flow diagram 8.00 Actions
OTICS (Thailand) Co., Ltd. 20 Jun 2025 Priroj Neamjarn Development Project progress work #679: Power meter monitoring New Requirement Multi filter the PowerMeter Name 8.00 Actions
OTICS (Thailand) Co., Ltd. 13 Nov 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS installation Rasberry Pi 8.00 Actions
OTICS (Thailand) Co., Ltd. 17 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Test and Deploy to server 8.00 Actions
OTICS (Thailand) Co., Ltd. 17 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Deploy to server 8.00 Actions
OTICS (Thailand) Co., Ltd. 16 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Include rate to function for calculate in system. 8.00 Actions
OTICS (Thailand) Co., Ltd. 16 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Include rate to function for calculate in system. 8.00 Actions
OTICS (Thailand) Co., Ltd. 13 Sep 2024 Phatthadon Inthachot Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS installation Cooling unit 8.00 Actions
OTICS (Thailand) Co., Ltd. 13 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Create a form for setting rates. 8.00 Actions
OTICS (Thailand) Co., Ltd. 13 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Create a form for setting rates. 8.00 Actions
OTICS (Thailand) Co., Ltd. 12 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Change the function cost bar chart to an energy cost bar chart 8.00 Actions
OTICS (Thailand) Co., Ltd. 12 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Change the function cost bar chart to an energy cost bar chart 8.00 Actions
OTICS (Thailand) Co., Ltd. 07 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast and receive real-time log power 8.00 Actions
OTICS (Thailand) Co., Ltd. 07 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast and receive real-time log power 8.00 Actions
OTICS (Thailand) Co., Ltd. 06 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast 8.00 Actions
OTICS (Thailand) Co., Ltd. 06 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast 8.00 Actions
OTICS (Thailand) Co., Ltd. 05 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast 8.00 Actions
OTICS (Thailand) Co., Ltd. 05 Sep 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix function forecast 8.00 Actions
OTICS (Thailand) Co., Ltd. 22 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix bug receive log data 8.00 Actions
OTICS (Thailand) Co., Ltd. 22 Aug 2024 Priroj Neamjarn Development Project progress work #679: Power meter monitoring Fix bug receive log data 8.00 Actions
OTICS (Thailand) Co., Ltd. 20 Aug 2024 Nattapol Poeam Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Install and debug program 8.00 Actions
OTICS (Thailand) Co., Ltd. 20 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring Installation 4.00 Actions
OTICS (Thailand) Co., Ltd. 20 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring Installation 4.00 Actions
OTICS (Thailand) Co., Ltd. 19 Aug 2024 Nattapol Poeam Installation Project progress work #645: [ Installation&On-site support ] Power meter monitoring system for OTICS Installation 8.00 Actions
OTICS (Thailand) Co., Ltd. 19 Aug 2024 Priroj Neamjarn Installation Project progress work #679: Power meter monitoring make manual and installation 8.00 Actions