Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 66.00

Project Date User Activity Issue Comment Hours
Asteer (Thailand) Co., Ltd. 23 Nov 2023 Santi Srichankaew Development Project progress work #38: Devolop and debug PLC Mitsubishi Q Series deverlop program complete 8.00 Actions
Asteer (Thailand) Co., Ltd. 23 Nov 2023 Santi Srichankaew Installation Project progress work #110: [On-site support]Support after cutover Installation complate 8.00 Actions
Asteer (Thailand) Co., Ltd. 18 Nov 2023 Kamol Anekchatnuntakool Installation Project progress work #109: [On-site support]Support after cutover On site support -Install Software -Test Software -Modify Software 8.00 Actions
Asteer (Thailand) Co., Ltd. 18 Nov 2023 Ryo Nozaki Installation Project progress work #240: [Installation&On-site support] Handy terminal for Pokayoke system Install complete and we must modification of some comment 6.00 Actions
Asteer (Thailand) Co., Ltd. 16 Nov 2023 Santi Srichankaew Installation Project progress work #110: [On-site support]Support after cutover 4.00 Actions
Asteer (Thailand) Co., Ltd. 07 Nov 2023 Santi Srichankaew Development Project progress work #110: [On-site support]Support after cutover Waiting iastallation on site 8.00 Actions
Asteer (Thailand) Co., Ltd. 02 Nov 2023 Santi Srichankaew Development Project progress work #38: Devolop and debug PLC Mitsubishi Q Series BT connect to PLC Mitsubishi Q03uvdcpu 8.00 Actions
Asteer (Thailand) Co., Ltd. 24 Oct 2023 Kamol Anekchatnuntakool Development Project progress work #21: Handy terminal application system Development. 8.00 Actions
Asteer (Thailand) Co., Ltd. 19 Oct 2023 Santi Srichankaew Development Project progress work #38: Devolop and debug PLC Mitsubishi Q Series 8.00 Actions
    (1-9/9)

    Also available in: Atom CSV