JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 30 Jan 2024 Nattapol Poeam Meeting Project progress work #328: Crate IoT data collection box for JATH Send demo box to Mantenance JATH team 4.00 Actions
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 25 Dec 2023 Nattapol Poeam Make document Project progress work #328: Crate IoT data collection box for JATH Summarize concept and equipment 8.00 Actions
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 24 Dec 2023 Nattapol Poeam Meeting Project progress work #328: Crate IoT data collection box for JATH Meeting and site survey and JATH Factory about box collect data and Change display 4.00 Actions
JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 18 Dec 2023 Nattapol Poeam Meeting Project progress work #328: Crate IoT data collection box for JATH Meeting and site survey and JATH Factory about box collect data and Change display 4.00 Actions