Hours: 973.50

Project Date User Activity Issue Comment Hours
ACME INDUSTRY CO.,LTD. 20 Sep 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support Online support about modify BOM&Planning 8.00 Actions
ACME INDUSTRY CO.,LTD. 22 Aug 2024 Arunwit Isarapongporn Installation Project progress work #603: Support Installation&On-site support 8.00 Actions
ACME INDUSTRY CO.,LTD. 21 Aug 2024 Arunwit Isarapongporn Installation Project progress work #603: Support Installation&On-site support 8.00 Actions
ACME INDUSTRY CO.,LTD. 10 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support On-site support 8.00 Actions
ACME INDUSTRY CO.,LTD. 09 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #603: Support On-site support 8.00 Actions
ACME INDUSTRY CO.,LTD. 02 Aug 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
ACME INDUSTRY CO.,LTD. 02 Aug 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 8.00 Actions
ACME INDUSTRY CO.,LTD. 01 Aug 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 8.00 Actions
ACME INDUSTRY CO.,LTD. 31 Jul 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 3.00 Actions
ACME INDUSTRY CO.,LTD. 30 Jul 2024 Kamol Anekchatnuntakool Development Project progress work #676: Develop HT Software for scan TAG. Develop HT Software for scan TAG. 8.00 Actions
ACME INDUSTRY CO.,LTD. 29 Jun 2024 Anonymous Meeting Project progress work #603: Support support 8.00 Actions
ACME INDUSTRY CO.,LTD. 21 Jun 2024 Anonymous Development Project progress work #603: Support FIX 8.00 Actions
ACME INDUSTRY CO.,LTD. 20 Jun 2024 Anonymous Development Project progress work #603: Support FIX 8.00 Actions
ACME INDUSTRY CO.,LTD. 19 Jun 2024 Anonymous Meeting Project progress work #603: Support meeting 8.00 Actions
ACME INDUSTRY CO.,LTD. 04 Jun 2024 Anonymous Meeting Project progress work #603: Support go get the problem 8.00 Actions
ACME INDUSTRY CO.,LTD. 21 May 2024 Anonymous Development Project progress work #603: Support Stock Inquiry Report 8.00 Actions
ACME INDUSTRY CO.,LTD. 08 May 2024 Anonymous Development Project progress work #93: [On-site support]Support after cutover 8.00 Actions
ACME INDUSTRY CO.,LTD. 07 May 2024 Anonymous Development Project progress work #478: [Coding]Handy terminal application modification task Injection handy 4.00 Actions
ACME INDUSTRY CO.,LTD. 06 May 2024 Anonymous Development Project progress work #478: [Coding]Handy terminal application modification task Part control handy 8.00 Actions
ACME INDUSTRY CO.,LTD. 08 Apr 2024 Kittisak Isarapongporn Development Project progress work #204: UAT about the WMS system and onsite support Fix issues in the punchlist 8.00 Actions
ACME INDUSTRY CO.,LTD. 08 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
ACME INDUSTRY CO.,LTD. 07 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
ACME INDUSTRY CO.,LTD. 06 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
ACME INDUSTRY CO.,LTD. 05 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
ACME INDUSTRY CO.,LTD. 04 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions