26 Nov 2024

13:59 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
Soraya Norasing
13:54 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
modify HT and support usert Soraya Norasing
13:52 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
modify HT and support usert Soraya Norasing
13:52 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
modify HT and support usert Soraya Norasing
13:52 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
modify HT and support usert Soraya Norasing
13:56 8.00 hours (Project progress work #593 (Close request): [Coding] Warehouse management system handyterminal Java)
modify HT Soraya Norasing
13:55 8.00 hours (Project progress work #593 (Close request): [Coding] Warehouse management system handyterminal Java)
modify HT and create document manual Soraya Norasing

25 Nov 2024

22:14 8.00 hours (Project progress work #593 (Close request): [Coding] Warehouse management system handyterminal Java)
Soraya Norasing

19 Nov 2024

23:22 8.00 hours (Project progress work #594 (In Progress): [Coding] Warehouse management system handyterminal PHP web)
Fix bugs before training and adjust code based on the client's requested changes. Ronnagon Kongsuwan
23:17 8.00 hours (Project progress work #594 (In Progress): [Coding] Warehouse management system handyterminal PHP web)
Developed Page Purchase Instructions and stock card current stock. Ronnagon Kongsuwan
23:15 8.00 hours (Project progress work #594 (In Progress): [Coding] Warehouse management system handyterminal PHP web)
Install website and build database server Ronnagon Kongsuwan
23:14 8.00 hours (Project progress work #594 (In Progress): [Coding] Warehouse management system handyterminal PHP web)
trainning user Ronnagon Kongsuwan
16:44 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Trial day 1 Kittisak Isarapongporn
16:42 2.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Pick up the printer from office Kittisak Isarapongporn

17 Nov 2024

23:44 7.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:43 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
23:43 8.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Final SIT Kittisak Isarapongporn
23:43 4.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
Kittisak Isarapongporn
 