Hours: 55963.60

Date User Activity Issue Comment Hours
21 Jul 2025 Priroj Neamjarn Development Project progress work #1010: Warehouse management system -Fix new Request 8.00 Actions
21 Jul 2025 Thanthima Phaengkham Installation Project progress work #1018: Calculate stock CKD end month [Task] LAT - Calculate stock CKD end month -Phase 4 — UAT & Performance Tuning 1/7 8.00 Actions
18 Jul 2025 Nattaporn Chaiya Development Project progress work #1448: [Coding] Schedule Schedule 8.00 Actions
18 Jul 2025 Kittisak Isarapongporn Development Project progress work #673: [Settings] Asprova implementation 8.00 Actions
18 Jul 2025 Thanthima Phaengkham Make document Project progress work #1018: Calculate stock CKD end month [Task] LAT - Calculate stock CKD end month -Phase 3 — Software Documentation 1/1 8.00 Actions
18 Jul 2025 Taweesak Prumvised Development Project progress work #843: [Cording] Warehouse system for business improvement for NKT Android Fixed issues of picking function. 8.00 Actions
18 Jul 2025 Priroj Neamjarn Development Project progress work #1010: Warehouse management system -Fix new Request 8.00 Actions
18 Jul 2025 Priroj Neamjarn Development Project progress work #1010: Warehouse management system -Fix new Request 8.00 Actions
18 Jul 2025 Nattaporn Chaiya Development Project progress work #910: Back-End Web dashboard application PHP Fix issues Basic Unit 8.00 Actions
18 Jul 2025 Yuki Osawa Make document Project progress work #1017: Project Management for Task Review 1.00 Actions
17 Jul 2025 Kittisak Isarapongporn Meeting Project progress work #647: [Coding]ASI - Process Control System Phase2 -C# Windows app 2.00 Actions
17 Jul 2025 Kittisak Isarapongporn Meeting Project progress work #867: [Documentation] IKD - Get requirements of project 2.00 Actions
17 Jul 2025 Kittisak Isarapongporn Meeting Project progress work #902: [Documentation] Get requirements of project 4.00 Actions
17 Jul 2025 Thanthima Phaengkham Development Project progress work #1018: Calculate stock CKD end month [Task] LAT - Calculate stock CKD end month -Phase 3 — Unit Testing 2/2 8.00 Actions
17 Jul 2025 Yuki Osawa Meeting Project progress work #1016: Asprova Phase 2 Implementation Had a meeting with Kamimura-san 3.00 Actions
17 Jul 2025 Yuki Osawa Make document Project progress work #1017: Project Management for Task Review 3.00 Actions
17 Jul 2025 Taweesak Prumvised Development Project progress work #505: [Coding] Warehouse management system handyterminal Java Fixed issue outbound. 5.00 Actions
17 Jul 2025 Taweesak Prumvised Meeting Project progress work #843: [Cording] Warehouse system for business improvement for NKT Android Support online fix issues. 3.00 Actions
17 Jul 2025 Nattaporn Chaiya Development Project progress work #910: Back-End Web dashboard application PHP Fix issues 8.00 Actions
17 Jul 2025 Priroj Neamjarn Development Project progress work #1010: Warehouse management system Training user WIP inbound, FG inbound 8.00 Actions
17 Jul 2025 Priroj Neamjarn Development Project progress work #1010: Warehouse management system Training user WIP inbound, FG inbound 8.00 Actions
16 Jul 2025 Kittisak Isarapongporn Meeting Project progress work #692: Design and get requirements 4.00 Actions
16 Jul 2025 Kittisak Isarapongporn Meeting Project progress work #873: [Documentation] Get requirements of project 4.00 Actions
16 Jul 2025 Thanthima Phaengkham Development Project progress work #1018: Calculate stock CKD end month [Task] LAT - Calculate stock CKD end month -Phase 3 — Unit Testing 1/2 8.00 Actions
16 Jul 2025 Yuki Osawa Meeting Project progress work #1016: Asprova Phase 2 Implementation Had a meeting with Nakao-san 1.00 Actions