Project

General

Profile

Spent time

Filters

Apply Clear

Hours: 55963.60

Date User Activity Issue Comment Hours
17 Feb 2024 Anonymous Installation Project progress work #445: [Installation&On-site support]Project Stock management system for MAS-T 8.00 Actions
17 Feb 2024 Suthiwat Banrueangthong Development Project progress work #400: Program developer and Dashboard design Test the signal to the dashboard and fix any signal mismatches. 8.00 Actions
17 Feb 2024 Nattapol Poeam Installation Project progress work #225: CCTV Installation Support at Site 8.00 Actions
17 Feb 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
17 Feb 2024 Ryo Nozaki Meeting Project progress work #442: [Installation&On-site support]Project Stock management system for MAS-T 14.00 Actions
17 Feb 2024 Arunwit Isarapongporn Installation Project progress work #309: [Requirement definition] Knuckle Line MC25&MC26 Traceability system mod Check data and modify application of Traceability system Line MC25&MC26. 8.00 Actions
17 Feb 2024 Soraya Norasing Installation Project progress work #102: [Installation&On-site support]Project Stock management system for MAS-T Installation&On-site support 8.00 Actions
17 Feb 2024 Suchin Viyasing Installation Project progress work #431: Wiring on the cabinet 18 set. Wiring cable in the cabinet 8.00 Actions
17 Feb 2024 Kittisak Isarapongporn Installation Project progress work #103: [Installation&On-site support]Project Stock management system for MAS-T Installation&On-site support 8.00 Actions
17 Feb 2024 Santi Srichankaew Development Project progress work #124: [Installation&On-site support] Production IoT system for JATH Deverlop PLC calculate bekido function JTEKT 8.00 Actions
17 Feb 2024 Kamol Anekchatnuntakool Development Project progress work #440: Order Sheet System PC. Develop Order Sheet System PC. 8.00 Actions
16 Feb 2024 Anonymous Installation Project progress work #445: [Installation&On-site support]Project Stock management system for MAS-T 8.00 Actions
16 Feb 2024 Suthiwat Banrueangthong Development Project progress work #400: Program developer and Dashboard design Test the signal to the dashboard and fix any signal mismatches. 8.00 Actions
16 Feb 2024 Nattapol Poeam Installation Project progress work #225: CCTV Installation Support at Site 8.00 Actions
16 Feb 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
16 Feb 2024 Ryo Nozaki Meeting Sales support #449: Sales for new and follow up each customer 10.00 Actions
16 Feb 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
16 Feb 2024 Soraya Norasing Installation Project progress work #102: [Installation&On-site support]Project Stock management system for MAS-T Installation&On-site support 8.00 Actions
16 Feb 2024 Kittisak Isarapongporn Installation Project progress work #103: [Installation&On-site support]Project Stock management system for MAS-T Installation&On-site support 8.00 Actions
16 Feb 2024 Santi Srichankaew Development Project progress work #124: [Installation&On-site support] Production IoT system for JATH Deverlop PLC calculate bekido function JTEKT 8.00 Actions
16 Feb 2024 Suchin Viyasing Design Project progress work #446: [ Task ] Drawing design for Master control box Design drawing 8.00 Actions
16 Feb 2024 Kamol Anekchatnuntakool Development Project progress work #440: Order Sheet System PC. Develop Order Sheet System PC. 8.00 Actions
15 Feb 2024 Suthiwat Banrueangthong Development Project progress work #400: Program developer and Dashboard design Test the signal to the dashboard and fix any signal mismatches. 8.00 Actions
15 Feb 2024 Panupong Raksakit Development Project progress work #410: [ Task ] Program and Dashboard Development Program and Dashboard Development 8.00 Actions
15 Feb 2024 Arunwit Isarapongporn Installation Project progress work #8: Support installation for power supply and LAN cable for 50 points Installation&On-site support 8.00 Actions
(5876-5900/7308) Per page: 25, 50, 100

Also available in: Atom CSV