Hours: 55963.60

Date User Activity Issue Comment Hours
02 Mar 2024 Anonymous Development Problem-Bug #76: NSET - Reprint FG slip & Traceability system by Handy fix repack 8.00 Actions
02 Mar 2024 Panupong Raksakit Taking Day off Project progress work #517: Panupong Raksakit Taking Day off January-December 2024 8.00 Actions
02 Mar 2024 Ryo Nozaki Installation Project progress work #442: [Installation&On-site support]Project Stock management system for MAS-T 12.00 Actions
02 Mar 2024 Kittisak Isarapongporn Development Project progress work #466: [Coding] PHP web function and web socket API Staging WS API development 8.00 Actions
02 Mar 2024 Soraya Norasing Development Project progress work #131: [Coding]Android handy and tablet modification Java development print tag receive & tag maker, development printer setting function 8.00 Actions
02 Mar 2024 Nattapol Poeam Installation Project progress work #126: [Installation&On-site support] Production IoT system for TNF On-site installation 8.00 Actions
02 Mar 2024 Suchin Viyasing Installation Project progress work #460: [Installation&On-site support] Production IoT system for JATH Support on site at JTEKT. 8.00 Actions
02 Mar 2024 Soraya Norasing Meeting Project progress work #447: create manual document for MAST Meeting with K.Pamp to explain what changes were made to the manual. 1.00 Actions
02 Mar 2024 Kamol Anekchatnuntakool Development Project progress work #130: [Coding]Inner packing screen function C# Develop Inner packing screen function C#. 8.00 Actions
02 Mar 2024 Jidapha Mangkhachot Development Project progress work #450: Development web display 8.00 Actions
01 Mar 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
01 Mar 2024 Anonymous Development Problem-Bug #76: NSET - Reprint FG slip & Traceability system by Handy fix reprint 8.00 Actions
01 Mar 2024 Panupong Raksakit Taking Day off Project progress work #517: Panupong Raksakit Taking Day off January-December 2024 8.00 Actions
01 Mar 2024 Ryo Nozaki Installation Project progress work #442: [Installation&On-site support]Project Stock management system for MAS-T 10.00 Actions
01 Mar 2024 Kittisak Isarapongporn Development Project progress work #466: [Coding] PHP web function and web socket API Staging WS API development 8.00 Actions
01 Mar 2024 Soraya Norasing Development Project progress work #131: [Coding]Android handy and tablet modification Java development print tag receive & tag maker 8.00 Actions
01 Mar 2024 Suchin Viyasing Design Project progress work #460: [Installation&On-site support] Production IoT system for JATH Design drawing Jtekt 8.00 Actions
01 Mar 2024 Soraya Norasing Meeting Project progress work #447: create manual document for MAST Check the correctness of the manual. 1.00 Actions
01 Mar 2024 Soraya Norasing Development Project progress work #459: support user for process control system 1) The customer wanted the program to be able to run ahead of time. The API has been revised. To be able to scan work in advance. 2)Found a problem, unable to access the diebond menu. From 29/02/24 4 p.m. to 01/03/24 9 a.m. No cause found yet But can come back to use by itself at 9 a.m. 2.00 Actions
01 Mar 2024 Soraya Norasing Meeting Project progress work #347: Meeting about modify display on TV meetting with K.pam about database and query of this project 2.00 Actions
01 Mar 2024 Nattapol Poeam Installation Project progress work #126: [Installation&On-site support] Production IoT system for TNF Install and uninstall EP02 for setting IP Address 8.00 Actions
01 Mar 2024 Kamol Anekchatnuntakool Development Project progress work #130: [Coding]Inner packing screen function C# Develop Inner packing screen function C#. 8.00 Actions
01 Mar 2024 Jidapha Mangkhachot Development Project progress work #450: Development web display 8.00 Actions
29 Feb 2024 Arunwit Isarapongporn Meeting Project progress work #94: [On-site support]Support after cutover Support to start using WMS the system for handy terminal & pegasus system 8.00 Actions
29 Feb 2024 Panupong Raksakit Taking Day off Project progress work #517: Panupong Raksakit Taking Day off January-December 2024 8.00 Actions